54. Deputy Willie O'Dea asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the progress made to date under the National Strategic Outcome (NSO) 9 of the National Development Plan 2021-2030; and if he will make a statement on the matter. [51315/26]

Comment on this
Jack Chambers Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation Fianna Fáil

As Minister for Public Expenditure Infrastructure Public Service Reform and Digitisation, I am responsible for setting the overall capital allocations across Departments and for monitoring monthly expenditure at Departmental level. The responsibility for the management and delivery of individual investment projects or sectoral policy strategies, within the allocations agreed under the National Development Plan (NDP), rests with the individual sponsoring Department in each case. Each Minister is responsible for deciding on the priority programmes and projects that will be delivered under their remit within the NDP and for setting out the timelines for delivery.

The NDP contains expenditure commitments for a range of strategic investment priorities which will contribute towards the achievement of the National Strategic Outcomes (NSOs), including NSO 9 which relates to the Sustainable Management of Water, Waste and other Environmental Resources. This NSO highlights the importance of sustainable water resources to the implementation of the National Planning Framework in order to underpin our environmental and economic well-being into the future. Investment in the water and wastewater network will support environmental and economic wellbeing, and deal with population growth and the effects of a changing climate.

The relevant sectoral strategies under this NSO are the Water Services Policy Statement 2018-2025, Uisce Éireann’s National Water Resources Plan and the Government’s Waste Action Plan for a Circular Economy. These strategies play a critical role in identifying the goals and priorities for this area and are therefore critical in informing the investment projects set out in the NDP.

In terms of water management, a range of investments are planned and underway under the NDP. Some recently completed projects include:

• The Enniscorthy Water upgrade scheme completed in June

• The Athlone Main Drainage and Wastewater project completed in April

• Phase 2 of the Leixlip Water treatment plant also completed in April

• The Ringsend Water treatment plant completed in February

Under NSO 9, Uisce Éireann is investing €12.2 billion of combined investment supports into the network from 2025-2029.

Further details of projects and programmes being delivered under NSO 9 can be found in the capital investment tracker provides a composite update on the progress of all major investments with an estimated cost of greater than €20 million. Accompanying the tracker, the myProjectIreland interactive map details projects across the country and provides details on specific projects by county and contains smaller investments such as schools and social housing projects. Search facilities also allow citizens to view projects in their regional area, by city, by county or by eircode.

The Project Ireland 2040 capital investment tracker and myProjectIreland interactive map are all available on gov.ie/2040.

In addition to the tracker, the sectoral plans which were published by Departments at the end of 2025 include planned investment and projects across the country, including a range of projects and critical infrastructure works. These sectoral plans are available on each Departmental website and will provide the Deputy with further detail on a sectoral basis.