Dáil

Written answer

School Facilities

1192. Deputy Noel McCarthy asked the Minister for Education and Youth the funding options available to schools to improve school access and safety for pupils through the development of a new entranceway or vehicle set down area; and if she will make a statement on the matter. [55887/26]

Comment on this
Hildegarde Naughton Minister for Education and Youth Fine Gael

I should explain that applications relating to the provision of funding for issues relating to an existing school building can fall under a number of different delivery mechanisms including, most frequently, the Summer Works Scheme and the Emergency Works Scheme and could include the upgrade or provision of entrances or set down areas.

The purpose of the Emergency Works Scheme (EWS) is to provide funding specifically for unforeseen emergencies, or to provide funding to facilitate inclusion and access for pupils with special needs. It does so by ensuring the availability of funding for urgent works to those schools that are in need of resources as a result of an emergency situation.

An emergency is deemed to be a situation which poses an immediate risk to health, life, property or the environment, which is sudden, unforeseen and requires immediate action, and in the case of a school, if not corrected would prevent the school or part thereof from opening.

The EWS operates on the basis of a minimal scope works to address the emergency situation. The EWS is intended to remedy an emergency situation and usually provides only an interim measure until a permanent solution can be delivered under the Summer Works Scheme (SWS) which deals with upgrade works to the school.

The EWS is open to primary and post primary schools with permanent recognition and in non-rented accommodation.

To make an application schools must complete the online Emergency Works Application Form available through the Esinet system.

The purpose of the SWS is to enable individual school authorities to undertake small-scale building works on a devolved basis and, ideally, can be carried out during the summer months or at other times that avoid disrupting the operation of the school.

The Climate Action Summer Works Scheme (which was previously named the Summer Works Scheme) places a strong emphasis on sustainability. Schools can now undertake additional measures such as insulation upgrades, LED lighting installation, EV charger provision, bike rack facilities to support active travel and other climate-focused works alongside traditional maintenance.

The newly announced Climate Action Summer works opened for applications on the 1st May and the application window closed on the 30th of June 2025, full details of the scheme can be found under www.gov.ie/en/department-of-education/services/summer-works-scheme/ The EWS is open for applications year-round. It is open to the school to make an application under the most appropriate scheme.

Comment on this