Written answer
Schools Building Projects
1273. Deputy Mark Ward asked the Minister for Education and Youth the plans for new schools or school extension within Dublin Mid-West due to the population increases; the funding associated with these; and if she will make a statement on the matter. [57077/26]
Comment on this
I wish to advise the Deputy that requirement for school places is kept under on-going review in the context of available information on population, enrolments and residential development activity.
In order to plan for school provision and analyse the relevant demographic data, the department divides the country into 314 school planning areas and uses a geographical information system, using data from a range of sources, including CSO census data, child benefit and school enrolment data, to identify where the pressure for school places across the country will arise and where additional school accommodation is needed at primary and post-primary level.
Major new residential developments have the potential to alter the demand for school places at a local level. In that regard, as part of the demographic demand analysis, the department monitors planning and construction activity in the residential sector. This involves the analysis of data sources from local authorities and the CSO along with the engagement with local authorities and the construction sector. In this way, up-to-date information on significant new residential developments is obtained and factored into the demographic analysis exercise. This is necessary to ensure that schools infrastructure planning is keeping pace with demographic changes, at a local level, where there is a constantly evolving picture with planned new residential development.
My department also conducts granular analysis below the level of a school planning area, particularly where a school planning area encompasses both high growth urban settlement areas and a more rural hinterland. Our analysis of school place demand in urban areas experiencing high population growth has indicated that demand in the urban area can be 10-20% higher than the school planning area as a whole.
If additional accommodation is required, the aim to try and facilitate this, as much as possible, by way of expansion of existing schools rather than establishing new schools. The expansion of existing schools is consistent with wider Government objectives under Project Ireland 2040 for an increased emphasis on compact growth.
New schools are only established in areas of demographic growth as the resources available for school infrastructure have to be prioritised to meet the needs of areas of significant population increase so as to ensure that every child has a school place.
Any future shortfall in capacity required to meet the demand for post primary schools can be catered for in the existing post primary schools.
Requirements for school places will be kept under ongoing review in this region and across the country.
Since 2020, my department has invested over €7 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,500 school building projects along with circa 4,300 small-scale improvement works to meet priority maintenance needs and advance energy efficiency and climate goal. In addition, repurposing and optimisation of existing accommodation capacity across the school estate has been a key enabler of timely, local provision of special class capacity in a way that supports best practice in inclusion and integration. Circa 80% of new special classes in 2025/26 are being facilitated in repurposed classroom accommodation. This investment has delivered real benefits for school communities.
A total capital allocation of €7.55 billion for the Department of Education and Youth has been confirmed for the period 2026-2030 under the National Development Plan. As part of this NDP allocation my department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs. In relation to project rollout for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project rollout over the course of 2026 to 2030 period to meet the most urgent and prioritised needs.
Our NDP Implementation Plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.
I can confirm that since 2020 my department has provided €1988.33 million in capital funding for Dublin schools. Over this period, a total of 273 schools have been upgraded either through provision of a new school building, a large-scale extension or provision of modular accommodation. In addition, 20 school projects which are to go to tender or construction in 2026 and 2027 were included in the NDP Implementation Plan. Furthermore, there are currently 43 school projects in Dublin under construction. This summer, 53 schools are approved to undergo works as part of the Climate Action Summer Works Scheme.
In addition, since 2020 a total of 541 special classes have been sanctioned in Dublin, of which 140 were sanctioned for September 2026.
Details of the progression of all projects approved by my department and up to date information relating to the latest stage of progress is available at www.gov.ie.