Written answer
Departmental Schemes
146. Deputy Sorca Clarke asked the Minister for Climate, Energy and the Environment the measures being taken to reduce waiting times for applicants to the SEAI warmer homes scheme; and if he will make a statement on the matter. [60942/26]
Comment on this
210. Deputy Brian Brennan asked the Minister for Climate, Energy and the Environment the measures that are in place to reduce the waiting time for those under the warmer homes scheme. [63619/26]
Comment on this
I propose to take Questions Nos. 146 and 210 together.
The Warmer Homes Scheme aims to improve the energy efficiency and warmth of homes owned by people at risk of energy poverty by providing fully funded retrofits. The scheme is operated by the Sustainable Energy Authority of Ireland (SEAI) on behalf of my Department and is funded through the carbon tax revenues and the European Regional Development Fund.
The Warmer Homes Scheme is available to owner-occupied properties, based on the householder being in receipt of certain Department of Social Protection income supports. The scheme targets support to those on the lowest incomes who are living in the least efficient homes so that the resources available can have the greatest impact in addressing energy poverty.
The average waiting time under the Warmer Homes Scheme, from application to completion of upgrade works, in 2025 was 22 months.
The breakdown of average waiting times under the scheme in 2025 was as follows:
• Application to Pre-BER Published - 6.5 months
• Application to Survey Completed - 13.5 months
• Application to Contractor Allocation - 14.8 months
• Application to Works Completed - 22 months
This represents a decrease from an average waiting time of 26 months for homes completed in 2022. In parallel with this decrease in the average waiting time, the number of homes upgraded in a year has almost doubled over the same period, increasing from over 4,200 in 2022 to over 8,100 in 2025.
The SEAI publish indicative wait times on their website for each stage of the process. This is available here: www.seai.ie/grants/home-energy-grants/fully-funded-upgrades-for-certain-homeowners.
The reduction in waiting times and increase in number of homes upgraded follows a range of measures introduced by my Department and the SEAI. These include:
• the allocation of additional staff to the Warmer Homes Scheme;
• a significantly increased budget allocation;
• active contract engagement and management by the SEAI to increase contractor output; and
• actions to address ongoing supply chain pressures.
The SEAI have established a new €1.2 billion contractor panel this year. This will support continued growth with a focus on scale, quality and output under the scheme.
The SEAI have also developed a Waiting List Action Plan with the objective of reducing the number of clients waiting for an upgrade, ensuring prioritisation of the worst performing homes, and improving efficiencies across the scheme.
To help maximise delivery and continue to improve waiting times, Budget 2026 provided record funding of €340 million for the Warmer Homes Scheme, with a target of 11,500 fully funded home upgrades for 2026.
The information sought regarding the maximum waiting period under the Warmer Homes Scheme from initial application to home survey and from application to completion of works; the number of households currently waiting for a home survey and for works to commence; and the number of applicants who have been waiting for more than 12, 18 and 24 months respectively, is an operational matter for the SEAI. The SEAI has established a specific email address for queries from Oireachtas members so that such queries can be addressed promptly and in line with the SEAI’s objective to deliver services to the highest standards. The email address is: oireachtas@seai.ie.