Dáil

Written answer

Rail Network

618. Deputy Eoghan Kenny asked the Minister for Transport whether any disciplinary, performance-management or other accountability process has been undertaken in respect of the management of the failed Iarnród Éireann Traffic Management System project; if so, the number of such processes undertaken; if not, the reasons; and if he will make a statement on the matter. [64003/26]

Comment on this

619. Deputy Eoghan Kenny asked the Minister for Transport to identify each Iarnród Éireann capital project, service expansion or other investment which has been or is expected to be rephased, postponed or reprioritised arising from expenditure associated with the failed Traffic Management System project and/or increased costs associated with the National Train Control Centre; and if he will make a statement on the matter. [64004/26]

Comment on this

623. Deputy Eoghan Kenny asked the Minister for Transport whether any planned enhancement to Cork commuter rail services, Cork-Dublin rail services or associated rail infrastructure will be delayed, rephased or otherwise affected by additional expenditure associated with the failed Iarnród Éireann Traffic Management System project or increased costs associated with the National Train Control Centre; and if he will make a statement on the matter. [64005/26]

Comment on this

635. Deputy Eoghan Kenny asked the Minister for Transport the expenditure incurred by Iarnród Éireann on external legal advice, consultancy, technical advice, reviews, arbitration, mediation or other dispute-resolution processes relating to the failed Traffic Management System project; and if he will make a statement on the matter. [64125/26]

Comment on this

636. Deputy Eoghan Kenny asked the Minister for Transport the amount recovered to date from contractors or other parties arising from the failed Iarnród Éireann Traffic Management System project; whether further recovery is being pursued; the total amount which Iarnród Éireann or the State is seeking to recover; and if he will make a statement on the matter. [64124/26]

Comment on this

637. Deputy Eoghan Kenny asked the Minister for Transport the total expenditure incurred to date on the failed Iarnród Éireann Traffic Management System project; the amount written off; the additional expenditure now estimated to be necessary to procure and implement a replacement traffic management system; the resulting total estimated Exchequer exposure; and if he will make a statement on the matter. [64123/26]

Comment on this
Darragh O'Brien Minister for Transport Fianna Fáil

I propose to take Questions Nos. 618, 619, 623, 635, 636 and 637 together.

Under the Dublin Transport Authority Act 2008, the National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area (GDA), including the National Train Control Centre, or NTCC. The NTA also manages the wider portfolio of public transport investment nationally.

Noting the NTA's responsibility in this matter, I have referred the Deputy's questions to the NTA for a direct, detailed reply. Please contact my private office if you do not receive a reply within 10 days.