Written answer
Road Projects
634. Deputy Eoghan Kenny asked the Minister for Transport the current estimated total cost of delivering the N72-N73 Mallow Relief Road; the expenditure on the project to date; the expenditure projected for 2027; how the current estimated cost compares with previous estimates; and if he will make a statement on the matter. [64114/26]
Comment on this
639. Deputy Eoghan Kenny asked the Minister for Transport the current status of the N72-N73 Mallow relief road; the date on which the preliminary business case was or is expected to be submitted to Transport Infrastructure Ireland; the expected date for submission of a planning application to An Coimisiún Pleanála; the timeframe for planning, procurement and commencement of construction; and if he will make a statement on the matter. [64111/26]
Comment on this
I propose to take Questions Nos. 634 and 639 together.
As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you on the status of this project.
I can confirm that €600,000 has been allocated for the N72/73 Mallow Relief Road scheme in 2026.
Noting the above position, I have referred your question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.