Written answer

National Transport Authority

Summary

The Minister referred questions on 132 buses and storage costs to the NTA, noting 90 electric buses await charging infrastructure and planned deployment.

229. Deputy Richard Boyd Barrett asked the Minister for Transport regarding the recent purchase of 132 buses by the NTA, the number of publicly-owned buses that are currently not being used; when they will come into use; and the cost of storage and servicing any unused buses, both cumulatively and per-week. [64718/26]

Comment on this
Darragh O'Brien Minister for Transport Fianna Fáil

As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure, including the provision and upgrade of public bus fleets and bus depots.

Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a direct reply. Please contact my private office if you do not receive a reply within 10 working days.

I would like to note that over 250 battery-electric buses have been accepted into the Dublin Bus and Bus Éireann fleets across the country, including the operation of our first fully electric services in Limerick and Athlone. The electrification of the bus fleet is a key part of the BusConnects programmes and in our investment in public transport across the country more generally, helping to make a sustainable mode of travel even more sustainable.

There are 90 zero-emission double-deck battery-electric buses awaiting deployment pending the bringing on stream of charging infrastructure, of which 36 are destined for the GDA and 54 destined for Galway. Plans are in place for all GDA-bound buses to be in service by the end of this year, while all buses destined for Galway are currently programmed to enter service across late 2026 and early 2027.

Implementation of further phases of electrification at existing bus depots will be greatly assisted by the NTA's new Electric Bus Charging Infrastructure framework contract, which has been finalised and will be formally awarded shortly.