Dáil

Written answer

Coast Guard Service

Summary

The new Coast Guard facility is expected to be completed by December and fully operational by early 2027, with interim on-site crew accommodation.

164. Deputy Louise O'Reilly asked the Minister for Transport if he can advise when new accommodation (details supplied) will be completed; the date he expects the crews to be fully moved in and operating from this space; and if he will make a statement on the matter. [66147/26]

Comment on this
Seán Canney Minister of State at the Department of Transport Independent

In his capacity as Minister of State for International & Road Transport, Logistics, Rail & Ports, my colleague Seán Canney T.D, has responsibility for the Irish Coast Guard and the SAR Aviation Contract.

Bristow Ireland Ltd. has advised my Department that construction of the new facility identified by the Deputy is at an advanced stage and that it anticipates project completion by December of this year, with the expectation of being fully operational by early Q1 2027. The new facility includes crew accommodation, helicopter hangar, operations and office spaces. In the interim, duty crews are accommodated in dedicated on-site facilities.