Dáil

Written answer

Electricity Grid

110. Deputy John Connolly asked the Minister for Climate, Energy and the Environment the expected timetable for implementing the CRU's decision on shared grid connections for co-located renewable generation and battery storage. [66783/26]

Comment on this
Darragh O'Brien Minister for Climate, Energy and the Environment Fianna Fáil

The Commission for Regulation of Utilities (CRU) is responsible for grid connection policy, including hybrid connections. The CRU is an independent regulator, accountable to a Committee of the Oireachtas and not to me as Minister. The CRU was assigned responsibility for the regulation of the Irish electricity sector following the enactment of the Electricity Regulation Act, 1999 and subsequent legislation.

Under CAP 23, the CRU are tasked with ensuring that hybrid technology grid connections are facilitated. Currently it is possible to obtain a hybrid connection, for various forms of generation, on the Irish system for a single legal entity at a connection point. The CRU are working to develop policies to remove barriers to facilitate additional hybrid connections and have split this workstream into three parts: Removal of Installed Capacity Cap; Sharing of Maximum Export Capacity (MEC); and Supporting Multiple Legal Entities.

To date this work has included removing the Installed Capacity Cap and the publication of the CRU’s decision paper on Sharing of Maximum Export Capacity in April 2026. The CRU are now progressing work on allowing multiple legal entities to own separate generation assets behind a single connection point.

As part of the CRU decision on Sharing of Maximum Export Capacity the System Operators, EirGrid and ESBN Networks, were tasked with developing a roadmap outlining the steps required to implement MEC sharing. This implementation roadmap was published in June, and work is ongoing to deliver on its programme of activities.

The Deputy may wish to engage directly with the CRU, EirGrid and ESB Networks who have respective contact email addresses for Deputies (oireachtas@cru.ie, oireachtas@eirgrid.com, oireachtas@esb.ie).