Written answer
Rail Network
123. Deputy John Connolly asked the Minister for Transport if funding will be provided under the NDP for the double tracking of the rail line between Galway City and Athenry; the expected timeframe for the delivery of this project; and if he will make a statement on the matter. [66453/26]
Comment on this
My Department is working with the National Transport Authority and Iarnród Éireann to progress a number of rail projects in Galway, including double tracking of the line between Athenry and Galway.
To progress this project, last summer Iarnród Eireann appointed a multidisciplinary engineering consultancy and work commenced on the Galway Line Capacity Study. An emerging preferred option is expected to be identified later this year.
Works are also continuing at Oranmore station. This project will provide an additional platform and a passing loop, increasing capacity on the Galway to Athenry line. This project is scheduled to be completed and operational in late 2027 and will be of immediate benefit to the route.
Noting the NTA's responsibility in this matter, I have referred the Deputy's questions to the NTA for a direct, detailed reply. Please contact my private office if you do not receive a reply within 10 days.