Written answer
Road Network
€600,000 was allocated in 2026 for the N72/N73 Mallow Relief Road, with TII responsible for providing an update on its progress.
226. Deputy Eoghan Kenny asked the Minister for Transport for an update as of September 2026 on the Mallow relief road project, including if the timeline of the project progression is being met; and if he will make a statement on the matter. [67660/26]
Comment on this
As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you on the status of the Mallow Relief Road.
I can confirm that €600,000 has been allocated for the N72/N73 Mallow Relief Road scheme in 2026
Noting the above position, I have referred your question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.