Written answer
Coast Guard Service
The Arklow Coast Guard Station extension faces higher-than-expected costs; the Department is revising plans, prioritising volunteer welfare facilities, with timelines pending.
256. Deputy Malcolm Byrne asked the Minister for Transport further to Parliamentary Question No. 55313/26, to provide an update on the development of the Arklow Coastguard Station; and if he will publish the review that was carried out and to set out a timeframe for the completion of works. [67976/26]
Comment on this
Further to my previous reply, my Department and the Irish Coast Guard have completed their review of the preliminary plans and cost estimates submitted by the Office of Public Works for the proposed extension to Arklow Coast Guard Station.
The review found that the projected cost of the proposed works was significantly higher than originally anticipated. My Department is engaged with the OPW in adjusting the project so it can proceed at the earliest opportunity, prioritising the provision of suitable toilet and welfare facilities for the Coast Guard volunteers.
The Department anticipates the OPW will revert shortly with detailed timelines and cost estimates. My officials will continue to engage closely with the OPW to ensure delivery of this project in a timely manner.