Written answer

An Garda Síochána

Summary

Cloyne Garda Station’s accessibility and refurbishment works are substantially complete; handover awaits the contractor’s safety file, and final costs remain pending account completion.

266. Deputy Noel McCarthy asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation to outline the progress made, and total cost to date, with respect to the upgrade of a Garda Station (details supplied). [69492/26]

Comment on this
Kevin Boxer Moran Minister of State at the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation Independent

I can confirm that the Office of Public Works (OPW) has undertaken refurbishment and Universal Access works to Cloyne Garda Station.

Works included Provision of a Universal Access ramp, 3 car parking spaces one of which is a universally accessible parking space; a new stepped access to the Garda station building; Universal Access Counter; internal upgrade.

The refurbishment works are substantially completed, with the OPW awaiting the completion of the Safety File from the contractor before the station can be handed over to An Garda Síochána.

The cost of the above works will be available when final account is complete.