Dáil

Written answer

Broadband Infrastructure

Summary

Section 254 licensing is determined by each local authority, while excavation of public roads requires consent under the Roads Act; statutory-undertaker cables laid under roads are exempt from Section 254. The Minister has no role in individual licensing decisions, and telecommunications policy lies with another department.

366. Deputy Barry Ward asked the Minister for Housing, Local Government and Heritage whether standard Section 254 and MapRoad Licensing, MRL, frameworks between local authorities and telecommunications providers accommodate minor public footpath excavations for last-metre domestic broadband connections; and what guidance is provided to local authorities, including Dún Laoghaire-Rathdown County Council, to resolve lead-in infrastructure deficits between public footpaths and private curtilages in mature housing estates. [70392/26]

Comment on this
John Cummins Minister of State at the Department of Housing, Local Government and Heritage Fine Gael

Section 254 of the Planning and Development Act 2000, as amended ‘the Act’, provides for a licensing system for appliances and structures, placed on, above, under or along a public road, including footpaths. This section of the Act however does not apply to the erection, construction, placing or maintenance under a public road of a cable, wire or pipeline by a statutory undertaker.

The Act provides that a ‘public road’ has the same meaning as the Roads Act 1993, which defines it as “a road over which a public right of way exists and the responsibility for the maintenance of which lies on a road authority”.

A person applying for a licence must provide the planning authority with such plans and other information concerning the position, design and capacity of the appliance, apparatus or structure as the authority may require. A licence may be granted by the planning authority for such period and upon such conditions as may be specified, including conditions in relation to location, design, space taken up by appliance and the need to protect protected structures etc. Within the statutory framework, licensing is a matter for each individual local authority and I, as Minister, have no role in the matter.

In considering an application for a licence under section 254(5) of the Act, a planning authority shall have regard to the proper planning and sustainable development of the area, the relevant development plan, the number and location of existing appliances and the convenience and safety of road users including pedestrians.

Section 254(5A) of the Act outlines the licensing process in respect of an application for a licence to erect, construct, place or maintain overground electronic communication infrastructure and any associated physical infrastructure, including telecommunication poles. If a planning authority fails to make a decision within a period of 4 months commencing on the date of receipt of an application, a decision of the planning authority to grant a licence shall be deemed to have been made on the day following the expiration of that period of 4 months. Where a planning authority requests additional information from the applicant and has not made a decision within a period of 4 months of receiving the applicant’s response to the request, a deemed decision to grant a licence shall be deemed to have been made. A deemed decision to grant a licence shall be subject to the condition that the network operator concerned, in advance of commencement of the works, shall inform the planning authority concerned and the National Roads Authority or road authority where applicable.

Under section 254(6) any person may, in relation to the granting, refusing, withdrawing or continuing of a licence under this section or to the conditions specified by the planning authority for such a licence, appeal to An Coimisiún Pleanála. Under section 30 of the Act, I am specifically precluded from exercising any power or control in relation to any particular case with which a planning authority or the Coimisiún is or may be concerned, except in very specific circumstances, which do not apply in this case.

The Planning and Development Act 2024 (“Act of 2024”) was signed into law by the President on 17 October 2024. The Department is currently putting arrangements in place to implement a phased commencement of the remainder of the Act of 2024 to facilitate the transition to the new legislation across the planning system, taking into account the need to liaise with local authorities, planning bodies and other stakeholders.

Section 254 of the Act of 2000 will be replaced by sections 13 and 14 of the Act of 2024 on commencement of those sections. Section 13(4)(b) of the Act of 2024 ensures that there is a public notification process for such licence applications.

It should be noted that the existing provisions in the Planning and Development Act 2000 will remain in place until the relevant provisions in the Act are commenced.

Subsection (8) of Section 254 outlines that ‘A person shall not be entitled solely by reason of a licence under this section to erect, construct, place or maintain on, under, over or along a public road any appliance, apparatus or structure.’

Under Section 13 (10) of the Roads Act, 1993, it is illegal to excavate a public road without lawful consent. Where a road opening licence is required to excavate a section of public road, such as a carriageway, footway or associated landscaped area, such a road opening licence can be obtained from the relevant roads authority (such as the city or county council). Section 13 of the Roads Act 1993, as amended, falls under the responsibility of the Minister for Transport.

Policy responsibility for  telecommunications infrastructure is a matter for the Department of Culture, Communication and Sport.

Comment on this