Written answer
Flood Relief Schemes
The Whitechurch flood scheme is about 77% complete, with substantial completion planned by the end of 2026; temporary defences will be checked before forecast floods, and the council will provide sandbags. A review of the January 2026 flood is due to the council in the coming weeks, while a new working group will consider options to improve flood insurance availability and affordability.
225. Deputy John Lahart asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation with regard to the OPW/SDCC Whitechurch flood alleviation scheme, if he is satisfied that there are now in place sufficient mitigation and alleviation measures to ensure that flooding will not re-occur (details supplied) given that flood insurance is a serious difficulty for householders. [71726/26]
Comment on this
226. Deputy John Lahart asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation with regard to the OPW/SDCC Whitechurch flood alleviation scheme, when the promised post-flood investigation report will be published; and the stage the project is at. [71724/26]
Comment on this
I propose to take Questions Nos. 225 and 226 together.
The Whitechurch Stream Flood Alleviation Scheme (Whitechurch Stream FAS) is being progressed by South Dublin County Council with funding provided by the Office of Public Works (OPW), as part of the Government's commitment to support the delivery of flood relief schemes under the National Development Plan. The Scheme consists of river bank improvements, flood defence walls, increasing wall heights, the removal or replacement of low-level bridges, and the provision of trash screens. The Scheme is expected to provide flood protection from the Whitechurch Stream for some 52 residential and commercial properties when complete.
The construction of the Whitechurch Stream FAS is being undertaken by the OPW's direct labour force, with approximately 77% of the linear meters of flood defences completed to date. The substantial completion date for the Whitechurch Stream FAS is programmed for the end of 2026. Temporary flood defences will remain in place for the remaining duration of the construction phase, and will be rechecked for effectiveness ahead of all forecast flood events.
South Dublin County Council, that has responsibility for flood emergency response and planning, has advised that it will provide sandbags to local residents for flood mitigation, in advance of any future forecast flood events pending the Scheme's completion. The Scheme’s consultants are currently finalising the draft Flood Review Report for the flood event that occurred in January 2026, with an expectation that the report will be delivered to the Council in the coming weeks.
The Government recognises that flood risk is an increasingly significant challenge, with implications for households, businesses, the insurance market, and the State. The Department of Finance has lead policy responsibility for matters in relation to insurance, including flood insurance and has therefore prioritised reform in this area via the Action Plan for Insurance Reform 2025 - 2029. The Department of Finance has advised that it is currently engaging with multiple stakeholders on the development of a long-term strategic approach to the provision of flood insurance, to consider potential solutions, specific to Ireland, to increase the availability and affordability of flood insurance. In this light, the Government has recently agreed to the establishment of the Flood Insurance Protection Gap Working Group, which will assess various policy options to narrow the flood insurance protection gap.