Written answer
Departmental Schemes
Warmer Homes Scheme applicants are prioritised by application date, with the least efficient homes (BER E–G) moved ahead; disability or illness is not an additional criterion. In the first half of 2026, average waits were 13 months to survey, 15 months to contractor allocation and 23 months to completion; measures to cut delays include more contractors, a waiting-list action plan and €340 million in Budget 2026 funding.
25. Deputy Shónagh Ní Raghallaigh asked the Minister for Climate, Energy and the Environment the current wait time for applicants to the SEAI warmer home scheme to receive an initial assessment. [71771/26]
Comment on this
31. Deputy Seán Crowe asked the Minister for Climate, Energy and the Environment to report on the criteria used by the SEAI to prioritise the worst performing homes; and if this includes whether the occupant is suffering from a disability or long-term illness. [72159/26]
Comment on this
42. Deputy Michael Healy-Rae asked the Minister for Climate, Energy and the Environment the efforts being made to decrease waiting times for those waiting for the warmer home scheme. [72413/26]
Comment on this
I propose to take Questions Nos. 25, 31 and 42 together.
The Warmer Homes Scheme (WHS) aims to improve the energy efficiency and warmth of homes owned by people at risk of energy poverty by providing fully funded retrofits. The scheme is operated by the Sustainable Energy Authority of Ireland (SEAI) on behalf of my Department and is funded through carbon tax revenues and the European Regional Development Fund.
The scheme targets support to those on the lowest incomes who are living in the least efficient homes so that the resources available can have the greatest impact in addressing energy poverty. Over 8,100 homes were upgraded last year, 109% of the annual target.
Applications to the scheme are assessed on the basis of when they first apply to the SEAI. Homes with the worst Building Energy Ratings also known as BER (E, F or G) are then prioritised for works. No other prioritisation takes place under the scheme.
Under the WHS, a pre-works BER is an obligation mandated for EU funding via the ERDF. The BER rating enables the SEAI to prioritise the worst performing homes and it is also key in determining the increase in energy efficiency as a result of the works upon completion.
Over 8,060 upgrades were completed under the scheme to end September 2026, an increase of 34.5% on the same period last year. At the same time, 11,823 applications have been received to the WHS to end September compared to 7,905 in the same time window last year, an increase of 49.6%.
For the first half of the year, the current wait time from application to survey completed was 13 months. The average waiting time from application to contractor allocation under the scheme was 15 months. The overall waiting time from application to works completed was 23 months.
A range of measures have been introduced by my Department and the SEAI to reduce overall waiting times, including the establishment of a new €1.2 billion contractor panel this year with additional contractors. This will support continued growth with a focus on scale, quality and output under the scheme.
The SEAI has also developed a Waiting List Action Plan with the objective of reducing the number of clients waiting for an upgrade, ensuring prioritisation of the worst performing homes, and improving efficiencies across the scheme.
There are a number of new, higher, fixed-amount grants now available where the household is in receipt of one or more of the DSP payments granting WHS eligibility. These grants allow qualifying homeowners at risk of energy poverty to get these works done using their own SEAI-registered contractor in a shorter timeframe.
Depending on the home type the grants include:
• up to €2,500 for attic insulation for homes built up to 2011;
• up to €2,300 for cavity wall insulation for homes built up to 2011; and
• up to €9,000 for the installation of Solar PV panels for homes built up to 2025.
These grants have been set at 100% of the median costs for these measures under SEAI schemes and, therefore, should cover the cost for lower-income households. More information on how to apply is available at https://www.seai.ie/grants/home-energy-grants/homeowners-in-receipt-of-certain-Department-of-Social-Protection-payments
To help maximise delivery and continue to improve waiting times, Budget 2026 provided record funding of €340 million for the WHS, with a target of 11,500 fully funded home upgrades for 2026.