Written answer

Office of Public Works

Summary

OPW plans painting, window repairs and structural and fire-compliance upgrades at Portarlington Garda Station in 2026–27, but funding remains unconfirmed pending cost estimates.

67. Deputy Brian Stanley asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the funding currently allocated by the OPW for capital improvements and upgrades to the Garda station in Portarlington. [74420/26]

Comment on this
Kevin Boxer Moran Minister of State at the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation Independent

The Office of Public Works (OPW) can confirm that there is a schedule of maintenance and capital works planned for Portarlington Garda Station to include the following:

Exterior painting and window repairs.

Structural and Fire Compliance Upgrades.

These works are included in the 2026 OPW work-plan, with a phased commencement during 2026 - 2027.

A design team has been appointed and is in the process of developing a Structural and Fire Compliance upgrade project for the station. The OPW are not in a position to confirm the funding currently allocated for works at Portarlington Garda Station as a budget estimate has yet to be completed.

The commencement/completion dates for the scheduled works are subject to the final sign off of operational and design requirements by An Garda Síochána.