The prison population was 113% of operational capacity on 29 October 2026. The Government has allocated €495 million for prison construction, targeting more than 1,500 additional spaces by 2031, including expanded facilities and a new prison planned for Thornton Hall; six projects are being accelerated.
1246. Deputy Barry Ward asked the Minister for Justice, Home Affairs and Migration the position regarding any plans to provide for additional prison capacity at Thornton Hall. [75451/26]
Comment on this
1247. Deputy Barry Ward asked the Minister for Justice, Home Affairs and Migration the actions he is taking to address overcapacity in parts of the Irish Prison Service; and if there are any plans to expand prison capacity in any existing prison in Ireland. [75449/26]
Comment on this
1297. Deputy Shane Moynihan asked the Minister for Justice, Home Affairs and Migration the current operational capacity of the prison estate; the current prison population; the number of prisoners being accommodated in excess of the approved capacity of institutions; and if he will make a statement on the matter. [76306/26]
Comment on this
I propose to take Questions Nos. 1246, 1247 and 1297 together.
The Irish Prison Service has advised that information regarding prison capacity and the numbers of prisoners in custody is collated daily by the Irish Prison Service Statistics Unit and published on its website (www.irishprisons.ie). This information can be found in the Information Centre under Statistics & Information, Daily Prisoner Population. The direct link is: www.irishprisons.ie/information-centre/statistics-information/2015-daily-prisoner-population/.
As of 29 October 2026 , the Prison Population stands at 113% of Operational capacity. The Irish Prison Service is required to accept into custody all persons committed to prison by the Courts and has no role in determining the number of people sent to custody at any given time. Where the number of people in custody exceeds the maximum capacity in any prison, the Irish Prison Service makes every effort to manage this safely, including the use of Temporary Release where appropriate. All decisions on Temporary Release are taken on a case?by?case basis and the safety of the public is paramount.
I am acutely aware of the capacity constraints in our prisons and the resulting challenges faced by those who work and live in our prisons. The Government has allocated funding for significant building in the prison estate. On conclusion of the NDP Review in July 2025, I secured a record capital investment of €528 million from 2026 to 2030, of which €495 million is to be invested in building projects and in line with the Programme for Government, includes an overall target of delivering over 1,500 spaces by 2031.
Since 2024, 292 spaces have been constructed across the Prison Estate, with 126 constructed in 2024, 106 constructed in 2025 and 60 spaces constructed so far in 2026. There are plans to build another 10 spaces by the end of the year and 102 in 2027.
In July and August this year, I signed contracts to increase the prisons’ capacity at the Dóchas Centre and Cloverhill Prison by over 300 spaces. On 8 September 2026 I signed the contract for the Midlands Prison Circular Landings Project, a significant development that will provide 102 additional prison spaces at Midlands Prison.
The building programme also envisages a large extension to the existing Cork Prison and a new block in Wheatfield. This is in addition to spaces created at Mountjoy, the Dóchas Centre, the Midlands Prison, and Limerick Men’s Prison. The record capital allocation will also allow for work to start on the planning and development of a new prison on the Thornton site in North County Dublin. A master plan for the site is expected to be developed this year.
The IPS capital programme is being delivered on a phased basis, with the sequencing and timelines of individual projects dependent on progression through the stages set out in the Infrastructure Guidelines. These guidelines, issued by the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation, establish the value-for-money and approval requirements that must be met before projects can advance to the next stage.
To support the timely delivery of additional prison capacity, I am accelerating the delivery of six projects, by moving directly to Approval Gate 2 of the Infrastructure Guidelines. This accelerated delivery measure is expected to reduce delivery timelines by between 12 and 18 months.