Written answer
Flood Relief Schemes
Piltown and Freshford are Kilkenny pilots testing a local-authority-led approach to data gathering for Tranche 2 flood schemes; design work has not yet commenced. Inistioge and Thomastown are also Tranche 2 projects, with viable schemes identified to protect 34 and 135 properties respectively, but delivery is expected to continue beyond 2030.
559. Deputy Peter 'Chap' Cleere asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation for an update in relation to the Piltown flood relief scheme; and if he will make a statement on the matter. [75927/26]
Comment on this
560. Deputy Peter 'Chap' Cleere asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation for an update in relation to the Freshford flood relief scheme; and if he will make a statement on the matter. [75925/26]
Comment on this
561. Deputy Peter 'Chap' Cleere asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation for an update in relation to the Inistioge flood relief scheme; and if he will make a statement on the matter. [75924/26]
Comment on this
562. Deputy Peter 'Chap' Cleere asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation for an update in relation to the Thomastown flood relief scheme; and if he will make a statement on the matter. [75923/26]
Comment on this
I propose to take Questions Nos. 559, 560, 561 and 562 together.
To establish those communities that are at risk from significant flood events, the OPW completed the largest study of flood risk ever undertaken by the State in 2018. The OPW Catchment-based Flood Risk Assessment and Management (CFRAM) Programme was undertaken by engineering consultants on behalf of the OPW, working in partnership with local authorities. The CFRAM Programme studied 80% of Ireland’s primary flood risk and identified solutions that can protect over 95% of that risk.
The Government has committed €1.3 billion to the delivery of flood relief schemes over the lifetime of the National Development Plan to protect approximately 23,000 properties in communities that are under threat from river and coastal flood risk.
Since 2018, as part of a phased approach to scheme delivery, funding under the National Development Plan has allowed the OPW to treble work on flood relief schemes, through partnership with local authorities. Consequently, some 100 flood relief schemes are at design, planning or construction at this time.
To date, the OPW has invested some €590m in 57 completed flood relief schemes, which protect 13,640 properties nationwide and provide an economic benefit in damages avoided estimated to be in the region of €2bn. In 2025, over €100m was spent on delivering flood relief schemes. This is a record high annual expenditure and is reflective of progress in delivering flood relief schemes nationally.
As it is not feasible to deliver all flood relief schemes concurrently (due to constraints on the specialised engineering skills in the OPW, local authorities, and the consultancy market), the flood-relief delivery programme was sub-divided into two tranches, focusing initially on Tranche 1 schemes and those already in the delivery pipeline. The prioritisation of the first tranche of schemes was based on three criteria including: scale of projects, capacity to deliver a national programme, and maximising return on investment by reference to property numbers.
Under the national programme, work has yet to commence on the design of some 50 Tranche 2 flood relief schemes. A number of initiatives are underway, including the OPW piloting a new delivery model for flood relief schemes through four Tranche 2 schemes in counties Kilkenny and Donegal, which is referred to as the Tranche 2 Pilot. The two Pilot Projects for Kilkenny are Freshford and Piltown. The Tranche 2 Pilot is transferring the management of data gathering, as a first step in designing a scheme, from consultant engineers for a single scheme to the local authorities for all schemes in the Pilot. The Pilot means that data gathering, where feasible, may be scaled up from individual communities to all schemes in a county.
The Pilot will better inform the prioritisation of future schemes nationally and the scope of services required from consultants to design and facilitate construction of flood relief schemes. While it is anticipated that work to progress the Tranche 2 schemes will commence within the lifetime of the National Development Plan, the implementation of these schemes will continue post-2030.
Inistioge and Thomastown are each projects within Tranche 2. The CFRAM programme identified a viable project for Inistioge, with 34 properties to benefit from the implementation of that flood relief scheme. Similarly, CFRAM identified a viable project for Thomastown, with 135 properties to benefit from a flood relief scheme in that area. Budgets and benefitting properties for each Tranche 2 project will each be assessed, as appropriate, following their commencement.
In May 2026, I was pleased to announce the revised criteria for the Minor Flood Mitigation Works and Coastal protection Scheme. The revisions include the relaxing of some economic criteria, an increase in the upper threshold in funding for projects from €750,000 to €2 million, and an increase in the OPW contribution from 90% to 95% for approved funding above €300,000.
I have also expanded the scheme to provide for interim flood mitigation measures for communities where a major flood relief scheme is planned, but not yet complete. This will facilitate local authorities to introduce interim measures ahead of the completion of a main scheme.