Written answer
Schools Building Projects
The extension remains under technical and cost review and will be considered for the 2027 tender tranche alongside other projects, subject to funding priorities.
707. Deputy Peter 'Chap' Cleere asked the Minister for Education and Youth if she will consider including an application for a new school extension (details supplied) in her Department's Capital Plan for 2027. [76155/26]
Comment on this
The school to which the Deputy refers was approved to enter my Department’s pipeline for a project under the Additional School Accommodation (ASA) Scheme. The project will provide three general classrooms, one textiles room, two design and communication graphics (DCG) rooms, one science laboratory with a preparation area, one art room with an associated project store, and one home economics room. The project is devolved to the school authority for delivery.
The Stage 2b (Post-Planning) report was submitted to the Department in Q1 2026 and is currently under review from both a technical and cost perspective.
In February 2026, Department officials advised the school authority that the project remained under consideration in the context of National Development Plan (NDP) parameters and the overall prioritisation of capital investment across the school building programme. This position was reiterated at a meeting between Department officials and representatives of the school in September 2026, during which the current funding and prioritisation context under the NDP was discussed.
All school building projects, as they progress through the pipeline, must undergo the necessary due diligence outlined in the Infrastructure Guidelines and Capital Works Management Framework.
It is expected that the next tranche of projects to proceed to tender will be published in 2027. Prioritisation will continue over the coming months to identify this next tranche of projects. This will be informed by latest available demographic and capacity data, the department’s energy and condition inventory (the validation of which is due to be completed by early 2027, opportunities for phased development to prioritise the most urgent accommodation needs and consultation with patrons and management bodies. The project at this school will be considered as part of the prioritisation process, along with all other projects at the required stage of readiness.
The timing of a project moving from one stage to the next requires careful planning and takes account of factors such as compliance with all scope, design and cost requirements; timing of affordability; and the prioritisation necessary for the school building programme to remain within agreed annual funding allocations.