Written answer
Prison Service
A €528 million capital programme targets over 1,500 prison spaces by 2031, with six projects accelerated to cut delivery timelines by 12–18 months.
1296. Deputy Shane Moynihan asked the Minister for Justice, Home Affairs and Migration to provide an update on plans to deliver more than 1,500 additional prison spaces by 2031; the projected delivery timeline for each phase of the programme; and if he will make a statement on the matter. [76307/26]
Comment on this
I am acutely aware of the capacity constraints in our prisons and the resulting challenges faced by those who work and live in our prisons.
Government has allocated funding for significant building in the prison estate. On conclusion of the NDP Review in July 2025, I secured a record capital investment of €528 million from 2026 to 2030, of which €495 million is to be invested in building projects and in line with the Programme for Government, includes an overall target of delivering over 1,500 spaces by 2031.
Since 2024, 292 spaces have been constructed across the Prison Estate, with 126 constructed in 2024, 106 constructed in 2025 and 60 spaces constructed so far in 2026. There are plans to build another 10 spaces by the end of the year and 102 in 2027.
In July and August this year, I signed contracts to increase the prisons’ capacity at the Dóchas Centre and Cloverhill Prison by over 300 spaces.
On 8 September 2026 I signed the contract for the Midlands Prison Circular Landings Project, a significant development that will provide 102 additional prison spaces at Midlands Prison.
The building programme also envisages a large extension to the existing Cork Prison and a new block in Wheatfield. This is in addition to spaces created at Mountjoy, the Dóchas Centre, the Midlands Prison, and Limerick Men’s Prison. The record capital allocation will also allow for work to start on the planning and development of a new prison on the Thornton site in North County Dublin. A master plan for the site is expected to be developed this year.
The IPS capital programme is being delivered on a phased basis, with the sequencing and timelines of individual projects dependent on progression through the stages set out in the Infrastructure Guidelines. These guidelines, issued by the Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation, establish the value-for-money and approval requirements that must be met before projects can advance to the next stage.
To support the timely delivery of additional prison capacity, I am accelerating the delivery of six projects, by moving directly to Approval Gate 2 of the Infrastructure Guidelines. This accelerated delivery measure is expected to reduce delivery timelines by between 12 and 18 months.