Dáil

Written answer

Departmental Reviews

Summary

The revised school accommodation report remains under departmental review following clarifications; officials will continue engagement, but no completion date was provided.

743. Deputy Noel McCarthy asked the Minister for Education and Youth to provide an update on the assessment of a revised report for a school (details supplied); and when she expects this ongoing review process to conclude. [76576/26]

Comment on this
Hildegarde Naughton Minister for Education and Youth Fine Gael

This school was approved to enter the Department’s pipeline under the Additional School Accommodation Scheme for a project providing one mainstream classroom, one Special Education Teaching (SET) room, and the repurposing of existing accommodation to provide one Special Educational Needs (SEN) room.

The project has been devolved to the school authority for delivery and is currently at Stage 1/2a (detailed design)

The school initially submitted their Stage 1/2a Report that extended beyond the scope of works approved by the Department. As a result, the school was requested to submit a revised report aligned with the approved project scope.

The revised Stage 1/2a Report has since been received and reviewed in accordance with the Department's Infrastructure Guidelines, taking into account the priorities and funding framework set out under the National Development Plan. Following this review, a further request for information and clarification issued to the school.

The school has responded to this request and the matters raised are currently being considered by the Department as part of the ongoing review process.

All school building projects, as they progress through the pipeline, must undergo the necessary due diligence outlined in the Infrastructure Guidelines and Capital Works Management Framework.

The timing of a project moving from one stage to the next requires careful planning and takes account of factors such as compliance with all scope, design and cost requirements; timing of affordability; and the prioritisation necessary for the school building programme to remain within agreed annual funding allocations.

Department officials will continue their engagement with the school over the coming months to provide any necessary guidance.