Schools Building Projects
The joint project is at detailed design stage, with options under review and a stakeholder meeting planned to select a design for planning permission.
821. Deputy Shane Moynihan asked the Minister for Education and Youth for an update on school building projects at schools in Dublin Mid-West (details supplied). [77326/26]
Comment on this
The joint major building project is currently at an advanced stage of Architectural Planning - Stage 2(b) - Detailed Design. During this stage, statutory approvals are obtained and the project design is further progressed to reflect any conditions of planning.
This joint school building project will deliver a new extension and refurbishment of some existing accommodation to provide a 24 classroom primary school with classrooms for children with special educational needs, at both schools.
The schedule of accommodation was recently increased to include SEN accommodation and the design options submitted by the Design Team are being evaluated by my Department.
A meeting of all stakeholders is anticipated to be held in the near future, to discuss and agree a preferred option which can be further developed and prepared to be submitted for planning permission.