Written answer
Schools Building Projects
The Minister said Clare received €173 million since 2020, with five projects under construction, 19 in design, and further modular, climate and special-class initiatives underway.
58. Deputy Joe Cooney asked the Minister for Education and Youth to provide details of all school building projects with her Department in County Clare; the stage at which each of these projects is currently at; the dates at which each of these projects have completed and progressed, through each stage, by national or secondary school, in tabular form. [78090/26]
Comment on this
In recent years the department has delivered significant expanded school capacity in County Clare and continues to progress further important projects through the pipeline.
Since 2020, the Department of Education has provided in the region of €173 million in capital funding for County Clare schools. Over this period, a total of 39 schools in County Clare have been upgraded through provision of either a new school building, extension, modular accommodation or climate pathfinder projects.
There are currently 5 projects on site across County Clare including a large-scale extension and refurbishment project for Scoil Naomh Cnoc An Ein. Table 1 provides details of all projects currently in construction.
In addition, 19 large-scale and additional accommodation projects are progressing through the design pipeline: 5 at Preliminary Design (Stage 1), 5 at Developed Design (Stage 2a), 8 at Detailed Design (Stage 2b) including a new school building for Mol an Óige CNS and 1 at tender (Stage 3).
Table 2 provides details of all projects included on the prioritised projects list that are proposed to proceed to tender or construction in 2026/2027.
There are also a further 11 projects underway through the Modular Programme and the Climate Action Summer Works Scheme.
In addition, 50 special classes have been sanctioned in County Clare for September 2026.
The current status of all projects is set out under item number ten at the following link (www.gov.ie). This is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction.
Table 1. School Building Projects in Construction in County Clare
Roll No | School Name | Townland | School Type | Project Type
61920N | St. Flannan's College | Ennis | Post Primary | Modular Project
17583V | SN Cnoc An Ein | Knockanean | Primary | Extension & Refurbishment
04919H | Cratloe NS | Cratloe | Primary | Extension
20476O | Scoil na Mainistreach Quin Dangan | Quin | Primary | Extension
91447I | St. Caimin's Community School* | Shannon | Post Primary | Extension
*Included in 105 projects identified to progress to tender or construction during 2026 and 2027
Table 2. School Building Projects prioritised to progress to tender or construction during 2026 and 2027 in County Clare
Roll No | School Name | Townland | School Type | Project Type | Current Stage Of Project
Roll No | School Name | Townland | School Type | Project Type | Current Stage Of Project
17026M | Clarecastle NS | Clarecastle | Primary | Extension | Stage 3
91447I | St. Caimin's Community School | Shannon | Post Primary | Extension | Onsite
17957N | Holy Family Junior School | Ennis | Primary | 8: Climate Action & Curricular Requirements (excl. Science Labs) | Approved in the first tranche of CASWS approvals
18720K | Miltown Malbay BNS | Milltown Malbay | Primary | 9: Fabric Defects | Approved in the first tranche of CASWS approvals
19043W | New Quay NS | New Quay | Primary | 9: Fabric Defects | Approved in the first tranche of CASWS approvals
20041C | Convent of Mercy NS | Kilrush | Primary | 2: Climate Action & Roof Works | Approved in the first tranche of CASWS approvals
20447H | Kilmurry McMahon NS | Kilrush | Primary | 7: Climate Action & Windows Projects | Approved in the first tranche of CASWS approvals
61930Q | Coláiste Mhuire | Ennis | Post-Primary | 2: Climate Action & Roof Works | Approved in the first tranche of CASWS approvals
62010C | St. Joseph's Secondary School | Spanish Point | Post-Primary | 4: Climate Action & Mechanical Works | Approved in the first tranche of CASWS approvals
70900I | Scariff Community College | Scariff | Post-Primary | 5: Climate Action & Science Labs (incl. Gas Works) | Approved in the first tranche of CASWS approvals
70901K | St. Anne's Community College | Killaloe | Post-Primary | 5: Climate Action & Science Labs (incl. Gas Works) | Approved in the first tranche of CASWS approvals