Written answer
Schools Building Projects
The school’s Stage 2b report is under review; progression depends on NDP prioritisation, with no firm timeline and the next tender tranche expected in 2027.
52. Deputy Joe Cooney asked the Minister for Education and Youth the current status of a school building project (details supplied); to provide an update on when it will progress to the next stage. [78098/26]
Comment on this
This school was approved to enter my Department’s pipeline under the Additional School Accommodation Scheme for a project providing two mainstream classrooms for displaced classrooms and repurposing works to create a second special educational needs classroom with a central activities space. This project is devolved to the school authority for delivery.
As the deputy is aware, the Stage 2b Post Planning report was submitted to my department in Q3 2026, and the report is currently under review. Department officials were recently in contact with the school advising that the project remains under review in the context of NDP parameters and the overall prioritisation of capital investment.
All school building projects, as they progress through the pipeline, must undergo the necessary due diligence outlined in the Infrastructure Guidelines and Capital Works Management Framework.
The timing of a project moving from one stage to the next requires careful planning and takes account of factors such as compliance with all scope, design and cost requirements; timing of affordability; and the prioritisation necessary for the school building programme to remain within agreed annual funding allocations.
It is expected that the next tranche of projects to proceed to tender will be published in 2027. Prioritisation will continue over the coming months to identify this next tranche of projects. This will be informed by latest available demographic and capacity data, the department’s energy and condition inventory (the validation of which is due to be completed by late 2026/early 2027), opportunities for phased development to prioritise the most urgent accommodation needs and consultation with patrons and management bodies.
The project at this school will be considered as part of the prioritisation process, along with all other projects at the required stage of readiness. At this stage, it is not possible to provide a definitive timeline for the project. Progression to the next phase is contingent on the project being assessed and advanced in line with the prioritisation framework under the National Development Plan.