Written answer
Rail Network
DART+ West enabling works began on 28 October, with construction due next year and main-package procurement expected in December, subject to approvals.
34. Deputy Réada Cronin asked the Minister for Transport the timeline for the completion of the Dart+ project that is intended to serve Kilcock, County Kildare. [78280/26]
Comment on this
As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. Under the Dublin Transport Authority Act 2008, the National Transport Authority (NTA) has statutory responsibility for the provision of public transport infrastructure and services within the Greater Dublin Area. In the case of the DART+ programme, the NTA fulfils this statutory remit in collaboration with Iarnród Éireann.
With regard to the Deputy's specific questions regarding the timeline for delivery of DART+ West, this is a matter for the NTA and I have forwarded the Deputy's questions to the NTA for a more detailed reply. Please advise my private office if you do not receive a response within 10 working days.
Pending this more detailed reply, I note that early construction is due to commence next year on DART+ West next year. A sod-turning to mark the beginning of enabling works on DART+ West took place on 28 October. The Compulsory Purchase Order Process for DART+ West commenced in September 2026 and, subject to the necessary approvals under the Infrastructure Guidelines, procurement for the main construction packages is expected to commence in December.