Written answer
Renewable Energy Generation
41. Deputy Tony McCormack asked the Minister for Climate, Energy and the Environment the ways in which the Government's continued investment in renewable energy and grid infrastructure can be used to support regional economic development and attract new enterprise and employment to areas with significant renewable energy generation. [66521/26]
Comment on this
Climate Action Plan 2024 sets Governments targets for both renewable electricity generation and new conventional generation required to assist in decarbonising our electricity system. Delivering this generation throughout the country is required so that they can be integrated into and deliver for the electricity system. EirGrid and ESB Networks, have primary responsibility for upgrading our electricity system including planning and constructing new investments in the grid. They are accountable to the Commission for Regulation of Utilities.
However, investing in and ensuring a fit for purpose electricity grid is a key priority for Government and I regularly meet with EirGrid and ESB Networks to monitor the progress of the PR6 grid programme. The PR6 programme is unprecedented in scale. CRU has approved an investment of up to €18.9 billion in over 500 capital investment projects over the period 2026-2030. These include 29 major transmission infrastructure projects and 32 major distribution substations. 10 of these priority transmission projects are already in construction. One of the priority distribution projects is already completed and three further projects are in construction.
The system operators are making detailed information on the progress of these investments public. In December 2025 CRU published the Transmission Baseline Programme setting out the Transmission projects in PR6 along with associated delivery milestones. EirGrid publishes quarterly updates in respect of delivery against these milestones, available on their websites.
PR6 will see investments of varying scales throughout the country based upon system needs, facilitating housing growth, heat and transport electrification, while also driving industrial and economic growth in Ireland. While PR6 provides the building blocks, those who are seeking to bring new industrial demand to regions should engage with EirGrid or ESB Networks at the earliest opportunity to discuss their connection requirements.