Dáil

Written answer

Departmental Data

58. Deputy Brendan Smith asked the Minister for Climate, Energy and the Environment the timeline to enact the Electricity (Supply) (Amendment) Bill 2025. [76606/26]

Comment on this
Darragh O'Brien Minister for Climate, Energy and the Environment Fianna Fáil

The revised Heads of Bill for the Electricity (Supply) (Amendment) Bill 2026 were approved by Government in October 2026, along with referral of the Bill for Pre-Legislative Scrutiny. Officials have commenced engagement with the Office of Parliamentary Counsel and are preparing for engagement with the Joint Oireachtas Committee on Climate, Environment and Energy.

While the precise timing of the remaining legislative stages will be a matter for the Oireachtas and the Government's legislative programme, the expectation is that the Bill will progress through Pre-Legislative Scrutiny and detailed drafting during late 2026 and early 2027, with publication and progression through the Houses of the Oireachtas during 2027.

Importantly, the Government and ESB Networks are not waiting for the enactment of the legislation before taking action to strengthen network resilience. Following Storm Éowyn, ESB Networks delivered a €74.5 million Winter Resilience Programme and has continued to implement resilience measures across the network. These measures include:-

• the assessment of approximately 3,782km of electricity infrastructure in forestry areas;

• engagement with over 1,800 forestry owners;

• inspection and maintenance of approximately 25,000km of hedgerows;

• works on more than 12,000 damaged and diseased trees; and

• the completion of approximately 36km of high-priority forestry corridor works, with delivery expected to reach approximately 40km by the end of 2026.

In addition, the Commission for Regulation of Utilities Price Review 6 (PR6) provides for investment of up to €18.9 billion in Ireland's electricity networks between 2026 and 2030, including approximately €990 million in resilience and climate adaptation investment.

Subject to the successful completion of the remaining legislative stages and approval by the Oireachtas, the objective is to have the legislation enacted during 2027. The Bill will complement the substantial resilience measures already underway and support the continued strengthening of Ireland's electricity network.