Dáil

Written answer

Departmental Data

33. Deputy Erin McGreehan asked the Minister for Climate, Energy and the Environment for an update on plans to increase indigenously produced biomethane. [78017/26]

Comment on this
Darragh O'Brien Minister for Climate, Energy and the Environment Fianna Fáil

Delivery of the Government's target of up to 5.7 TWh of indigenous biomethane per annum by 2030 and its use within our energy system will have multiple cross-sectoral benefits for Ireland’s economy, energy security and emissions profile. As such, development of this industry is being advanced through a collaborative approach to policy implementation across all sectors including energy, agriculture and enterprise.

The Biomethane Implementation Group has been established to oversee implementation of the National Biomethane Strategy and delivery of the 25 key strategic actions to ensure the necessary infrastructure and supports are in place to support development of an indigenous biomethane industry of scale

Chaired by my Department, with close support from the Department of Agriculture, Food and the Marine, the Group reports directly to the Heat and Built Environment Taskforce. Membership of the group includes key Government Departments and Agencies, and industry representatives.

The Group continues to engage with action owners and key stakeholders to monitor implementation and a full progress report on delivery of actions within the National Biomethane Strategy is now published on the biomethane policy information page on the Gov.ie website. It is anticipated that a second progress report on delivery of actions will be published later in 2026.

Ireland’s biomethane sector is gaining significant momentum. Seven anaerobic digestion plants are currently under construction or have just completed construction, representing roughly 12% of our national production target.

My Department has launched an expression of interest for a capital grant scheme to further support the construction of biomethane facilities in Ireland. The Renewable Heat Obligation is being finalised and will drive demand in the sector.

Other recent deliverables include the connection policy for the national gas network, an interim solution for reverse compression requirements, and the opening of the central grid injection facility in Mitchelstown by Gas Networks Ireland.