Five Phase 1 offshore wind projects are currently in development, with planned capacity of 3.8 gigawatts. These projects are located off our east coast from County Louth down to County Wexford. All five projects have submitted planning applications in 2024 and 2025, and they have addressed or are very close to addressing Further Information requests from An Coimisiún Pleanála (ACP). The first planning determinations from An Coimisiún Pleanála are anticipated in the first half of 2027. Subject to planning approval, I anticipate that some or all of these projects will be in construction by 2030 and operational in the early 2030s.
The 900 megawatt Tonn Nua project off the coast of Waterford is progressing well since Helvick Head DAC was selected as the auction winner in December 2025. I understand that a planning determination is anticipated by 2030 and energisation of the project by 2033.
Tonn Nua is the first of four development zones from the South Coast DMAP being brought to auction. My Department is making preparations to develop the remaining three zones over the coming years.
Separately, my Department is advancing the National DMAP process which will designate sufficient additional renewable development areas around our coast to facilitate our longer term target of 20 gigawatts.
The international market situation for offshore wind has changed much since Ireland's first offshore wind auction in 2023. This presents challenges for all countries in progressing their offshore wind ambitions. I am maintaining regular dialogue with our ongoing offshore wind projects as we navigate these challenges. While this more challenging international market environment has the potential to impact on the timing of achievement of particular milestones in our offshore wind ambitions, Government remains committed to achieving those ambitions.