Written answer
Data Centres
56. Deputy Paul Murphy asked the Minister for Climate, Energy and the Environment to respond to the 'extreme disappointment' expressed by the Climate Change Advisory Council that new partially fossil fuel powered data centres are to be permitted, that this 'threatens Ireland's decarbonisation and climate targets', and if he will make a statement on the matter. [78265/26]
Comment on this
The Commission for Regulation of Utilities (CRU) is an independent regulator, accountable to a Committee of the Oireachtas. Section 34 of the Electricity Regulation Act 1999 provides that the CRU has the power to issue Directions to the Electricity System Operators in relation to the terms and conditions offered to parties seeking to connect to and use the electricity system.
While the concerns expressed by the Climate Change Advisory Council are noted with respect to the CRU Large Energy Users Connection Policy, it is important to recognise that the CRU Connection Policy was expressly designed to address concerns regarding sustainable data centre demand growth, grid constraints, security of supply and decarbonisation, while supporting renewable energy targets and minimising impacts on national carbon emissions.
The idea that current policy permits unconstrained growth does not reflect or recognise the Government's Large Energy User Action Plan (LEAP) or the CRU's connection framework and the strategic plan-led approach being taken that aligns future development with available grid capacity, network investment and renewable energy resources. There is no automatic entitlement to a connection with applications subject to detailed and substantial requirements against grid capacity and system constraints.
The connection policy incorporates a range of requirements designed to support broader renewable energy targets while maintaining security of supply and system reliability. New large data centres must secure dispatchable generation or storage to match their demand, with that capacity participating in the electricity market and operational before the data centre can commence operation. They must also meet at least 80% of their annual electricity demand from additional renewable electricity generated in Ireland, with non-compliance potentially resulting in reduced capacity or termination of the connection agreement. This approach also supports the transition towards a highly renewable electricity system.
Substantial progress has been made in Ireland’s wider energy transition and the electricity system now regularly generates 40-50% of its electricity from renewable sources, while greenhouse gas emissions are at the lowest level in over 30 years, demonstrating that economic growth and decarbonisation can progress together, including alongside contracted data centre demand.