Written answer
Electricity Supply Board
49. Deputy Barry Heneghan asked the Minister for Climate, Energy and the Environment following the submission of the ESB networks plug-in solar working group report to his Department on 1 October 2026, when the report and its recommendations will be published; the actions that are now required to permit the safe use of plug-in solar systems up to 800 watts; and whether he will provide a firm timeline for their introduction in Ireland. [78305/26]
Comment on this
At my request, ESB Networks established a plug-in solar working group in May 2026 to examine pathways for the safe, standardised and scalable deployment of the technology. The group has met nine times to date. The working group recently submitted an options report to my Department, setting out recommendations on matters including installation approaches, product specifications and customer guidance. It is the Working Group’s intention that this report will be published as soon as is possible. Timelines will depend on stakeholders' internal review processes and public accessibility requirements before the document can be made available online.
In parallel, my Department is working with stakeholders to progress elements of the regulatory framework. Planned next steps include an Ireland-specific safety assessment, a legislative review, development of a product specification, publication of detailed customer guidance, and the establishment of an online product registration portal.
Further work is required to ensure the technology can be deployed safely, is supported by an appropriate regulatory framework, and that any legal barriers are addressed. My Department is currently progressing the safety assessment and legislative review, both of which are expected to conclude next year.
Product standards are a matter for the National Standards Authority of Ireland, whereas ESB Networks is responsible for registration arrangements to support network visibility and compliance. While delivery timelines will depend on the work of these stakeholders, my Department is committed to working closely with them to expedite the introduction of plug-in solar in Ireland.