Written answer
Sports Facilities
321. Deputy Sorca Clarke asked the Minister for Culture, Communications and Sport for an update on the development of a new National Velodrome and Badminton Centre. [78462/26]
Comment on this
On 3 September 2025, the Government approved funding of €99.6 million and the appointment of Walls Construction as principal contractor for the National Velodrome and Badminton Centre (NVBC). Construction commenced in February of this year and I am pleased to inform the Deputy that the project is progressing well and is expected to be delivered on time and within budget.
Since the commencement of construction, significant progress has been made on the development of the groundworks and the erection of the steel frame for the building. In parallel with the main construction works, the design team for the project continues to progress plans for the timely fit-out to the facility, with a view to it being fully operational and in use by Q2 2028.
The Project will deliver a 250-metre cycling track, the standard required length for hosting major international events. It will also deliver up to 12 badminton courts in the in-track area, seating for 1,000 spectators and ancillary facilities.
When operational, the NVBC will address the need to provide world-class track cycling facilities for our athletes as well as providing the sport of badminton with integrated training, gym and medical facilities. This state of the art facility will afford our track cycling athletes the opportunity to train in Ireland and should have a positive effect on future international performance levels in both sports.