Written answer
Environmental Impact Assessments
236. Deputy Mairéad Farrell asked the Minister for Climate, Energy and the Environment whether Ireland has designated renewables acceleration areas in accordance with Article 15c of Directive (EU) 2023/2413; whether the plans and strategic environmental assessment required by that Article have been adopted; and the date on which the coordinated mapping required by Article 15b was completed. [78636/26]
Comment on this
Article 15b of the recast Renewable Energy Directive 2023/2413 (REDIII) requires EU Member States to carry-out national territory mapping, to identify the domestic potential and the available areas that are necessary for the installation of renewable energy plants and their related infrastructure as required, to meet Ireland’s national contributions towards the overall EU renewable energy target for 2030.
Additionally, the Directive requires Member States to ensure that competent authorities identity at least one Renewable Acceleration Area (RAA) (under Article 15c) which must be a “sub-set” of areas identified under the national territory mapping exercise.
The coordinated mapping and public consultation report in relation to Article 15b were finalised in July this year and submitted to the European Commission in September.
My Department has been begun the preparation of a draft plan for the designation of a Renewable Acceleration Area, as per Article 15c of REDIII. Further statutory Public Consultation on a draft plan for the designation of any Renewable Acceleration Area and the establishment of appropriate rules on effective mitigation measures will take place at a later date and in accordance with the requirements of Article 15d of REDIII.
The purpose of the Public Consultation is also to invite any key considerations from the public, in preparing a draft plan for the designation of at least one Renewable Acceleration Area, as required under Article 15c of REDIII.
Points raised in the submissions in relation to Renewable Acceleration Areas will be taken into consideration. Further statutory public consultation on a draft plan for the designation of any Renewable Acceleration Area and the establishment of appropriate rules on effective mitigation measures, will take place at a later date and in accordance with the requirements of Article 15d of REDIII.
The Draft RAA Plan will be prepared having regard to, and in accordance with, all relevant national, regional and local level policy frameworks and legislative requirements. This will include the relevant Regional Economic and Spatial Strategies (RSES) and County Development Plans, in force at the time of the making and adoption of the RAA Plan. This will also include relevant policy frameworks and legislative requirements.