314. Deputy Pat Buckley asked the Minister for Education and Youth whether her Department has received applications or requests from schools (details supplied) for the establishment of autism classes; the dates on which any such applications or requests were received; the current status of any associated capital or accommodation projects; the reasons for any delays in delivering these facilities; and if her Department has assessed the feasibility of using existing classrooms, temporary accommodation or modular facilities to establish post-primary autism classes by September 2027. [78651/26]

Comment on this
Hildegarde Naughton Minister for Education and Youth Fine Gael

Scoil Mhuire and Coláiste Treasa in Kanturk have been approved to enter my department's pipeline of projects under the Additional School Accommodation (ASA) scheme. Both school projects are devolved to Cork Education and Training Board (CETB) for delivery.

The project at Scoil Mhuire was approved in October 2021 and will provide nine mainstream classrooms (seven prefab replacements), five Special Education Tuition (SET) rooms, one Graphics room, one Music room, one Textiles room, and a two class Special Education Needs (SEN) base.

This project is currently at Stage 2a. The Stage 2a developed design report has been submitted to my department and is currently under review from a technical and cost perspective.

The project at Scoil Treasa was approved in November 2021 and will provide seven mainstream classrooms, five Special Education Tuition (SET) rooms, two Art rooms and two project stores, one Music room, one Multimedia room, one Textiles room, and a two class Special Education Needs (SEN) base.

This project is currently at Stage 1 (Preliminary Design). During this stage, site factors and constraints are assessed, options are developed for delivery of the project, and a preferred option is identified.

The original design team lead, appointed in September 2022, withdrew from the project in May 2025. A procurement process was subsequently undertaken to appoint a replacement, with a new lead appointed in September 2025. The transition between design teams has contributed to delays in the preparation and submission of the revised Stage 1 report.

Cork ETB submitted updated drawings in September 2026; however, the Department is still awaiting receipt of the fully revised Stage 1 report.

All school building projects, as they progress through the pipeline, must undergo the necessary due diligence outlined in the Infrastructure Guidelines and Capital Works Management Framework.

The timing of a project moving from one stage to the next requires careful planning and takes account of factors such as compliance with all scope, design and cost requirements; timing of affordability; and the prioritisation necessary for the school building programme to remain within agreed annual funding allocations.

To date, no applications have been received from CETB or the schools concerned seeking approval for SEN repurposing works involving the conversion of existing school accommodation to Special Education Needs classrooms.