Energy Policy
366. Deputy Ken O'Flynn asked the Minister for Enterprise, Tourism and Employment further to Parliamentary Question No. 75251/26, the date on which the implementation update on the Large Energy User Action Plan will be published; the status of each of the 17 enabling actions against the timelines set out in the plan, in tabular form; and whether the National Planning Statement for Green Energy Parks will be published before 31 December 2026. [78851/26]
Comment on this
Further to my reply to Parliamentary Question 75251/26, I have attached a table setting out the current status of each of the 17 enabling actions contained in the Large Energy User Action Plan (LEAP), including progress against the timelines set out in the Plan.
As previously noted, the 17 enabling actions contained within LEAP comprise a substantial and ambitious programme of policy, regulatory, planning and energy market development measures that will be progressed over a number of years. Many of these actions will be implemented on an iterative basis, requiring ongoing analysis, across Government engagement and in some instances further Government and independent regulatory decision-making.
It is my intention to provide a comprehensive implementation update on LEAP to the Cabinet Committee on the Economy, Trade and Competitiveness in early 2027, reflecting progress made during the first year since the publication of the Action Plan. This will provide a detailed overview of progress across all actions and next steps for implementation for the coming year.
As previously noted, it is currently intended to publish a draft National Planning Statement for Green Energy Parks during 2026, noting that this timeline will be contingent on a number of interdependencies and other factors, including provisions on the establishment of national planning statements set out in the Planning and Development Act, 2024, as amended.
Government is committed to the implementation of the LEAP and to advancing the policy, planning, regulatory and infrastructure measures necessary to support the sustainable development of strategic large energy user investment in Ireland.
Action No. | Action | LEAP Timeframe | Status | Update
1 | Multi-annual investment in electricity infrastructure | From 2026 | Ongoing | To unlock further electrification, Price Review 6 provides for up to €18.9bn investment in Ireland’s electricity network during 2026-30. This action will also consider whether anticipatory network investments could take place in respect of green energy parks Informed by EU Guidelines on same.
2 | Create an energy system plan | 2027 | In Progress | This action will be advanced during 2027, informed by outputs of Action 7.
3 | Design flexible or “non-firm” contracts for LEU connections | 2027 | In Progress | Following transposition of EU Regulation 2024/1711 amending Directive (EU) 2019/944 on common rules for the internal market for electricity, the Commission for Regulation of Utilities (CRU) has been designated as Ireland’s competent authority responsible for developing the framework for flexible connection agreements.
4 | Energy Network Tariffs, market operation and grid code redesign to deliver LEU demand flexibility | As per revised and expedited National Energy Demand Strategy (Including in respect of Actions 2.4, 2.6, 2.8, 2.9, 2.18) | In Progress | This action is being progressed by CRU under the framework of the National Energy Demand Strategy, as well as through likely complementary provisions in the forthcoming Energy Affordability Action Plan under preparation by the Minister for Climate, Energy and the Environment.
5 | Assess powers of system operators and CRU to facilitate plan-led demand locations | 2027 – position paper, followed by new legislation if required | Ongoing | This action is being progressed by the Department of Climate, Energy and the Environment and other relevant bodies during 2026/2027, linked to Action 1, 2 and 7.
6 | Legislate for and implement new Private Wire Policy | 2026 | In Progress | Draft legislation scheduled to be published by the Minister for Climate, Energy and the Environment in late 2026, contingent on Government approval.
7 | Model a range of LEU development scenarios | Q2 2026 | In Progress, with completion rescheduled for 2027 to align with EirGrid’s forthcoming Future Network Vision | Significant engagement between DETE, DCEE and EirGrid on this workstream has taken place during 2025-26, with work ongoing.
8 | Embed LEAP strategy in national spatial planning policy | 2026 | In Progress | National Planning Statement preparation has advanced, with the intention that a draft statement will be completed before the end of 2026. Timelines for this action will be informed by a number of interdependencies and other factors, including relevant provisions for the establishment of national planning statements within the Planning and Development Act, 2024, as amended.
9 | Establish Annual Data Centre Sector Roundtable | 2026 & onwards | Completed | The first annual Data Centre Sector Roundtable took place in October 2026.
10 | Develop a ‘Single Point of Contact’ for the Green Energy Parks | 2027 | In Progress | Work is progressing on the implementation of the EU’s Net Zero Industry Act (NZIA) framework, for a Single Point of Contact. The implementation and effectiveness of this approach will inform further consideration of the appropriate policy approach. I am also aware of further industrial policy at European level, including the Industrial Accelerator Act and the Cloud and AI Development Act, which may further inform our national approach to planning for Green Energy Parks.
11 | Support the further development of a CPPA “Route to Market” for offshore wind to supply green energy parks | 2027 | In Progress | The Department of Climate, Energy and the Environment (DCEE) carried out a pre-consultation on CPPAs in 2026. The targeted pre-consultation concluded with an analysis of responses and identification of key issues for further review. This pre consultation material will be integrated into a public policy consultation document for issue and is expected to go live in Q4 2026. Following review of all public submissions, the Department will publish a new CPPA Policy Framework in 2027.
12 | Establish real-time emissions reporting frameworks for LEUs | 2026 | In Progress | Ireland has been an active participant in EU level discussions regarding establishing an EU framework that will provide for completion of this action.
13 | Market design to support co-location | 2028 & ongoing | Ongoing | Under implementation via relevant and complementary workstreams within the National Energy Demand Strategy.
14 | Facilitate direct engagement with regional Green Energy Park proposers | 2026 & onwards | In Progress | Associated engagement has taken place during 2026 following publication of LEAP. Establishing a formal structure for future engagement is also taking place as part of DETE’s process to establish a Green Growth Strategy.
15 | Develop IDA Ireland ‘Next Generation Strategic Sites’ | Proposals 2025; Investments from 2030 | In Progress | IDA Ireland continues to progress this workstream, as per timelines set out in LEAP.
16 | Enterprise support innovation in energy management | 2025 workplan; 2026 Implementation | Ongoing | These objectives will inform DETE’s process to establish a Green Growth Strategy. Enterprise agencies and SEAI are exploring additional energy efficiency supports and grants for businesses. Measures within the forthcoming Energy Affordability Action Plan will further strengthen energy management and reduce costs.
17 | Establish an LEU ‘Sectors of the Future’ Council | 2026 | In Progress | Prospective expert participants have been identified, with associated participation invitations to issue before end of 2026.