Tourism Policy

368. Deputy Michael Cahill asked the Minister for Enterprise, Tourism and Employment to provide a detailed breakdown of the funding provided by Fáilte Ireland and Kerry County Council towards a facility (details supplied), including the total project cost, the amount of Fáilte Ireland funding approved and drawn down, and the contribution made by Kerry County Council; the original anticipated opening date and the revised expected opening date; the reason for the delay in bringing the facility into public use; and whether he will ensure that a definitive opening date is provided to the public. [78935/26]

Comment on this

369. Deputy Michael Cahill asked the Minister for Enterprise, Tourism and Employment the current status of the new €1.3 million water sports and outdoor activities facility at Fenit, County Kerry; the reasons the facility has not yet opened to the public despite being substantially complete; whether his Department has been informed of any outstanding commissioning, technical or operational issues; the expected date for the facility to open to the public; whether he will engage with Fáilte Ireland and Kerry County Council to ensure that the facility is opened without further delay. [78934/26]

Comment on this
Peter Burke Minister for Enterprise, Tourism and Employment Fine Gael

I propose to take Questions Nos. 368 and 369 together.

The Fenit Water Sports and Outdoor Activities Facility is a best-in-class outdoor tourism amenity designed to enhance the visitor experience and serve as a central hub for water-based activities in the region.

The project is one of several developments being delivered under Fáilte Ireland’s €32 million Platforms for Growth 2 capital investment programme, which is focused on creating high-quality infrastructure to support outdoor and water-based tourism across Ireland. These facilities are designed to provide a focal point for local communities and visitors alike, supporting a range of water sports operators while offering modern amenities including changing facilities, hot showers, lockers and toilets.  Fáilte Ireland has awarded funding of €1.39M for the Fenit Water Sports and Outdoor Activities Facility.

The appointed contractor commenced construction works on 24 March 2025, with an initial programme duration of 52 weeks, which indicated an anticipated completion date in March 2026. During construction, a number of unforeseen issues arose, including the diversion of underground services by third parties, additional foundation works required due to ground conditions encountered on site, and delays relating to the manufacture and delivery of bespoke materials. These factors impacted the overall project timeline.

A Certificate of Practical Completion was issued in June 2026, with the commissioning phase commencing in July 2026. This phase has included extensive testing and commissioning of building services together with the resolution of operational snagging items. These works are now substantially complete.

In addition to supporting tourism growth, the facility will provide an important resource for local swimming clubs, community groups, schools and organised tour groups. Accessibility and sustainability have been central to the project's design, with features including full wheelchair access, solar heating panels, a Changing Places facility and accessible toilet provision, ensuring the amenity can be enjoyed by the widest possible range of users.

While the main facility building has not yet opened to the public, outdoor showers, foot washes and public realm areas have been in use, and public toilet facilities are available on site. The ongoing works within the building have therefore not directly impacted public access to, or enjoyment of, the beach and associated amenities at Fenit.

Neither Fáilte Ireland nor the Department has been advised of any significant outstanding technical or operational issues beyond the completion of the commissioning process and final operational snagging works required prior to opening. Fáilte Ireland continues to engage with Kerry County Council, which is responsible for managing and delivering the project. Following completion of the remaining commissioning and handover activities, the facility is expected to be fully open to the public by the end of 2026.