Written answer
Schools Building Projects
418. Deputy Shane Moynihan asked the Minister for Education and Youth for an update on the approved two-class SEN base building project at a school (details supplied) following submission of its Stage 1 report in October 2025, including the timeframe for the project to progress to the next stage. [78987/26]
Comment on this
This school was approved to enter the Department’s pipeline under the Additional School Accommodation Scheme for a project providing one mainstream classroom and a two-classroom special educational needs base. This project is devolved to the school authority for delivery.
The Stage 1, Preliminary Design report was submitted to my department in October 2025. This report is currently under review from a technical and cost perspective. Department officials recently contacted the school to advise that the project remains under review in the context of NDP parameters and the overall prioritisation of capital investment.
All school building projects, as they progress through the pipeline, must undergo the necessary due diligence outlined in the Infrastructure Guidelines and Capital Works Management Framework.
The timing of a project moving from one stage to the next requires careful planning and takes account of factors such as compliance with all scope, design and cost requirements; timing of affordability; and the prioritisation necessary for the school building programme to remain within agreed annual funding allocations.
At this stage, it is not possible to provide a definitive timeline for the project. Progression to the next phase is contingent on the project being assessed and advanced in line with the prioritisation framework under the National Development Plan.