Written answer
Office of Public Works
341. Deputy Tom Brabazon asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the nature of refurbishment works that the OPW carried out at Coolock Garda Station in each of the years of 2025 and to-date in 2026; and if any fresh capital works projects are currently under consideration by OPW in respect of this station. [79045/26]
Comment on this
The Office of Public Works (OPW) can confirm that refurbishment Works were carried out at Coolock Garda Station as outlined in the table, below.
Year | Nature of Works
2025 | Upgrade to Public office, and Universal Access works to reception, entrance, external ramps Replacement of rear access doors and provision of new access controls Remedial works to cell floors and cell corridor
2026 | An Garda Síochána (AGS) National Infrastructure Upgrade Works Programme which includes M&E upgrade works primarily in ICT Rooms to facilitate the roll out of Body Worn Cameras by AGS
OPW are currently planning works to increase security of the site boundaries; this will include new vehicular electronic gates, a new pedestrian gate, new fencing and secure gates within boundary, and new railings to raise the height of the exiting walls.
It is also planned to apply anti - vandal film to the station windows.
The commencement dates for works are subject to final sign-off on design, funding, and operational requirements of An Garda Síochána (AGS).