Written answer
Flood Relief Schemes
345. Deputy Ken O'Flynn asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the impact of the judicial review proceedings brought in respect of the confirmation of the River Bride (Blackpool) drainage scheme in July 2026 on the timeline for the scheme; the stage the scheme had reached at the time the proceedings were initiated, including procurement and the appointment of a contractor; and the date by which construction had been expected to commence before the proceedings were brought. [79164/26]
Comment on this
346. Deputy Ken O'Flynn asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the number of properties in Blackpool, Cork, recorded as having flooded in each flood event since 2012; and the number of residential and commercial properties that will be protected by the River Bride (Blackpool) drainage scheme as confirmed in July 2026, compared with the number to be protected under the scheme as originally confirmed in March 2021. [79170/26]
Comment on this
347. Deputy Ken O'Flynn asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the interim flood protection measures in place for homes and businesses in Blackpool, Cork, pending the delivery of the River Bride (Blackpool) drainage scheme; whether any additional interim measures will be put in place given the further delay to the scheme; and whether the Office of Public Works has engaged with the insurance industry regarding flood cover for properties in Blackpool that will be protected by the scheme. [79169/26]
Comment on this
349. Deputy Ken O'Flynn asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation the total amount spent by the Office of Public Works on the River Bride (Blackpool) drainage scheme to date, broken down by design, environmental assessment, public consultation, legal costs and other costs; the current estimated total cost of the scheme; and the estimated additional cost arising from delays to the scheme since it was first confirmed in March 2021, in tabular form. [79166/26]
Comment on this
I propose to take Questions Nos. 345, 346, 347 and 349 together.
The River Bride (Blackpool) Scheme submitted for statutory confirmation provides protection against the 100-Year flood (1% Annual Exceedance Probability) for some 293 properties.
In accordance with the Arterial Drainage Act, 1945, the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation confirmed the River Bride (Blackpool) Drainage Scheme on the 14 July 2026.
Since then, the OPW and its engineering consultants mobilised resources to detail the design for the construction of the confirmed scheme, taking account of the conditions associated with the statutory confirmation. A programme for the commencement of the construction, including the number of properties to be protected by this confirmation, is significantly advanced.
The Scheme's Total Project Budget is €20.5m and total expenditure, to date, is €2.1m. While it is not possible to attribute expenditure directly to delays to the scheme since it was first confirmed in March 2021, expenditure is recorded by supplier. Expenditure since 2016 can be categorised as follows:
Engineering service | Environmental consultancy | Other | Total
€1,629,216 | €367,887 | €97,143 | €2,094,246
Other refers to expenditure for Local authority payments and consultancy services separate from main engineering (engineering service) and environmental consultants, including archaeology.
Cork City Council can introduce interim measures pending the scheme's completion. Funding of up to 95% for the associated costs can be made available from the OPW’s Minor Flood Mitigation Works and Coastal Protection Scheme.
In addition, and through once off OPW funding, Cork City Council expended €15,000, for channel clearance works at River Bride in Blackpool, in October 2026.
The OPW has a role to assist insurance companies to take into account the protection provided by completed flood defence schemes. In this regard, the OPW has a Memorandum of Understanding with Insurance Ireland, the representative body for the insurance industry. This Memorandum sets out principles of how the two organisations work together to ensure that appropriate and relevant information on these completed schemes is provided to insurers to facilitate, to the greatest extent possible, the availability to the public of insurance against the risk of flooding. While the Memorandum does not guarantee the availability of flood insurance, Insurance Ireland members have committed to take into account all information provided by the OPW when assessing exposure to flood risk within the protected areas.
The decision on whether to offer flood insurance, the level of premiums charged and the policy terms applied are matters for individual insurers. Insurance companies make commercial decisions on the provision of insurance cover based on their assessment of the risks they would be accepting on a case-by-case basis. The Government cannot interfere in the provision or pricing of insurance products, as reinforced by the EU framework for insurance (Solvency II Directive).
Insurance Ireland operates an Insurance Information Service for those who have queries, complaints or difficulties in relation to obtaining insurance, which can be contacted by phone at 01 676 1914 or by email at feedback@insuranceireland.eu. Similarly, Brokers Ireland, the representative body for insurance brokers in Ireland, has access to a wide range of providers and products, and can offer advice for customers when sourcing cover. Brokers Ireland can be reached by phone at 01 661 3067. Furthermore, where an individual considers that they have been treated unfairly, they have the option of making a complaint to the Financial Services and Pensions Ombudsman (FSPO). The FSPO can be contacted either by email at info@fspo.ie or by phone at 01 567 7000.
The Government recognises that flood risk is an increasingly significant challenge, with implications for households, businesses, the insurance market, and the State. The Department of Finance in its lead flood insurance policy role has therefore prioritised reform in this area via the Action Plan for Insurance Reform 2025 - 2029. The Department of Finance has advised that it is currently engaging with a multiple of stakeholders on the development of a long-term strategic approach to the provision of flood insurance, to consider potential solutions, specific to Ireland, to increase the availability and affordability of flood insurance.
In this light, the Government has recently agreed to the establishment of the Flood Insurance Protection Gap Working Group, which will assess various policy options to narrow the flood insurance protection gap. This approach will seek to ensure the market remains involved in the provision of cover and any proposed measure does not lead to a sharp increase in premiums, less risk reduction and fewer adaptation measures, lower risk awareness, or inadvertently widening rather than narrowing the insurance protection gaps over time.