Schools Building Projects

456. Deputy Eoghan Kenny asked the Minister for Education and Youth the number of schools currently awaiting funding under the summer works scheme, including applications carried forward from previous years; the average and longest waiting time for approval; the criteria used to prioritise applications; the number of projects approved under the scheme in each of the years 2023 to 2026 that have yet to be completed; the measures being taken to ensure that projects approved for summer 2027 are delivered within that timeframe; and if she will make a statement on the matter. [79177/26]

Comment on this
Hildegarde Naughton Minister for Education and Youth Fine Gael

The purpose of the Climate Action Summer Works Scheme (CASWS) is to enable individual school authorities to undertake small-scale building works on a devolved basis that, ideally, can be carried out during the summer months or at other times that avoid disrupting the operation of the school. The CASWS operates on a multi-annual basis across a number of categories of works.

The CASWS was open for applications from 1 May to 30 June 2025, during which more than 1,400 applications were received. To date, a total of 427 projects have been approved under the CASWS.

In November 2025, the Department announced the first tranche of approvals under the Scheme. Of these, 297 projects were approved to proceed in 2026, including 99 projects carried forward from the previous Summer Works Scheme.

The Department announced a second tranche of projects last week. A further 229 projects have been approved to proceed in 2027. The projects approved under this tranche were assessed and prioritised by the department based on the individual needs of schools and the urgency of the works required. A particular focus this year was supporting projects in special schools. The approved projects encompass a broad category of works and a wide geographical spread across 26 counties. This approach should help market engagement and facilitate the achievement of good value for money by schools in the procurement process. It is envisaged these works will take place predominantly in Summer 2027.

It is anticipated that the next tranche of approvals will be announced in the latter part of 2027.

The scheme is a multi-annual scheme, the last summer works scheme that opened for applications opened in April 2019 and that application window closed in June 2019. My department officials approved 1,183 projects under that scheme. No projects were approved in 2023 to 2025 until the new Climate Action Summer Works Scheme opened.

It should be noted that the Summer Works Scheme does not operate on the basis of a waiting list. Applications are received during a defined application period and are then assessed and prioritised on a multi-annual basis having regard to the nature, urgency and priority of the works proposed. Accordingly, applications that have not yet been approved are subject to ongoing consideration under the Scheme rather than being placed on a waiting list pending funding.

Approvals were issued well in advance to provide schools with adequate time to complete the necessary planning, procurement and governance processes. The Department also provides detailed guidance and support documentation to assist schools in delivering projects. This suite of documentation is available on the Departments website. Furthermore, schools have 24 months from the date of approval to complete works under the Scheme, providing flexibility to accommodate project delivery timelines.

The full list of applications approved for 2026 and 2027 can be found under: www.gov.ie/en/department-of-education/services/summer-works-scheme/.