Written answer

Housing Provision

709. Deputy John Paul O'Shea asked the Minister for Justice, Home Affairs and Migration for an update on the future of the rapid build houses for Ukrainians once they are no longer in use (details supplied). [79603/26]

Comment on this
Colm Brophy Minister of State at the Department of Justice, Home Affairs and Migration Fine Gael

In April 2022, the Government asked the Office of Public Works (OPW) to evaluate the feasibility of developing a rapid build, volumetric modular unit option to accommodate people fleeing the war in Ukraine. The modular units delivered under the Rapid Build Programme, were developed following a Government decision to proceed in June 2022.

In total, 654 homes were built across 11 locations, including 66 homes at the site identified by the Deputy accommodating 264 people. A total of 2,640 people are being accommodated across all 11 sites. Each adult occupant signs a license agreement, and a weekly contribution is payable at a rate of 16% of household income plus a fee of €40 for utilities.

The OPW developed an exemplar single-storey modular design for the programme, with a specification to ensure Building Regulation compliance. The design is also aligned with the Department of Housing’s equivalent space standards to allow the units to be potentially utilised for social housing at a future date. While the units as built comply with social housing size requirements for a one-bedroom apartment, modifications are possible to convert two units into one larger three- bedroom unit to accommodate a family of five.

The homes are highly energy efficient, durable units with a minimum 60-year lifespan and the development of the sites has been conducted in an environmentally sustainable way to support long term residency and to ensure that, post development, local areas are enhanced. Each site has roads, footpaths, street lighting, community facilities, including green spaces, fully in line with Local Authority planning guidance.

While the Temporary Protection Directive is in force, a planning exemption is in place to allow the use of the sites for temporary accommodation for the Ukraine response. This means that, at this time, the homes cannot be utilised for any other purpose. Alternative future use of the rapid build homes, however, following the cessation of the Directive has always been a fundamental element of the programme and was an integral part of the design of the homes and site layouts.

To determine the long-term strategy for the sites post Temporary Protection Directive, a multi-stakeholder process commenced in March 2025, chaired by officials from this Department and including representation from the OPW and the Department of Housing, Local Government and Heritage. In tandem with the consideration of the feasibility of potential future uses, this work involves exploring planning regularisation at each site.

To date, there has been no final decision made on long term future use, as discussions are ongoing with the need to explore all potential options within the local areas.

Preparatory work on planning regularisation has been advanced and relevant Local Authorities are in the process of re-zoning the sites concerned to residential under a Local Development Plan variation process, where this is not already the case; this work is expected to be completed by the end of 2026.