98. Deputy Martin Kenny asked the Minister for Education and Youth the reason stage 2a approval for a school (details supplied) has not yet been granted; and if she will provide an update on the application. [79863/26]

Comment on this
Hildegarde Naughton Minister for Education and Youth Fine Gael

This school was approved to enter the Department’s pipeline under the Additional School Accommodation Scheme for a project providing six mainstream classrooms, two special education tuition (SET) rooms and two special education Needs (SEN) classrooms. This project is devolved to the school authority for delivery.

The project is currently at Stage 2a, Developed Design.  During this stage, the project design is further developed, cost planning is progressed and preparations are made to submit the project for statutory approvals.

The Stage 2a, Developed Design report was submitted to my department earlier this year. This report is currently under review from a technical and cost perspective.

All school building projects, as they progress through the pipeline, must undergo the necessary due diligence outlined in the Infrastructure Guidelines and Capital Works Management Framework.

The timing of a project moving from one stage to the next requires careful planning and takes account of factors such as compliance with all scope, design and cost requirements; timing of affordability; and the prioritisation necessary for the school building programme to remain within agreed annual funding allocations.

The accommodation needs at this school will be considered as part of the ongoing overall department-led prioritisation process, in consultation with the school’s patron and school authorities. Progression to the next phase is contingent on the outcome of the review and the project’s alignment with the prioritisation framework under the National Development Plan.