Written answer
Schools Building Projects
118. Deputy Michael Murphy asked the Minister for Education and Youth the current status of a building project at a school (details supplied) sanctioned in 2020 and currently at Stage 2B, with planning permission granted in June 2025; the outstanding requirements preventing progression to tender and construction; and whether the project will be prioritised for inclusion in the 2027 school building programme, given the severe accommodation pressures affecting 700 students, including six special classes. [80114/26]
Comment on this
This school was approved to enter my Department’s pipeline under the Additional School Accommodation Scheme for a project providing a two classroom special educational needs (SEN) base, two special education tuition (SET) rooms, one technology room and preparation area, one project store, two science labs and preparation area, one design and communication graphics (DCG) room, one home economics room, one textiles room, one multi-media room and ancillary.
This project is devolved to the school authority for delivery.
The project is currently at Stage 2b, Detailed Design. During this stage, statutory approvals are obtained and the project design is further progressed to reflect any conditions of planning. My department is currently awaiting submission of the Stage 2b report from the school authority.
Upon receipt, my department will undertake a detailed review from a technical and cost perspective
All school building projects, as they progress through the pipeline, must undergo the necessary due diligence outlined in the Infrastructure Guidelines and Capital Works Management Framework.
The timing of a project moving from one stage to the next requires careful planning and takes account of factors such as compliance with all scope, design and cost requirements; timing of affordability; and the prioritisation necessary for the school building programme to remain within agreed annual funding allocations.
It is expected that the next tranche of projects to proceed to tender will be published in 2027. Prioritisation will continue over the coming months to identify this next tranche of projects. This will be informed by latest available demographic and capacity data, the department’s energy and condition inventory (the validation of which is due to be completed by late 2026/early 2027), opportunities for phased development to prioritise the most urgent accommodation needs and consultation with patrons and management bodies.
The project at this school will be considered as part of the prioritisation process, along with all other projects at the required stage of readiness.