Rail Network
63. Deputy Réada Cronin asked the Minister for Transport the timeline for the delivery of the DART+ programme to Maynooth; and the projected commencement and completion dates for works on the Maynooth Line. [80215/26]
Comment on this
As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. Under the Dublin Transport Authority Act 2008, the National Transport Authority (NTA) has statutory responsibility for the provision of public transport infrastructure and services within the Greater Dublin Area. In the case of the DART+ programme, the NTA fulfils this statutory remit in collaboration with Iarnród Éireann.
With regard to the Deputy's specific questions regarding the DART+ West project, this is a matter for the NTA and I have forwarded the Deputy's questions to the NTA for a more detailed reply. Please advise my private office if you do not receive a response within 10 working days.
Pending this more detailed response, DART+ West is a high priority for this Government and is being progressed accordingly. A major milestone was marked on 28 October, when enabling works began on DART+ West with a sod-turning ceremony held at Dunboyne Station.
Funding secured under the National Development Plan will see early infrastructure construction start on DART+ West next year. DART+ West must commence first among the DART+ projects as it represents the crucial enabler of the rest of the programme, delivering depot capacity to house an expanded electrified rail fleet and city centre capacity upgrades.
The Compulsory Purchase Order process has also commenced, with notices to treat issued to over 200 affected landowners on the route in September.