Ceisteanna ar Sonraíodh Uain Dóibh - Priority Questions ›

Rail Network

Summary

The Minister reaffirmed the Government’s commitment to DART+ South West, with both it and DART+ West expected to go to Cabinet in the coming weeks and share procurement frameworks to speed tendering. The Deputy cited a possible contract by end-2028 and services by 2034; the Minister also said additional rail carriages would be redeployed to high-demand areas and NTA bus services would be detailed in December.

102. Deputy Shane Moynihan asked the Minister for Transport for an update on the delivery of DART+ South West; the progress made on funding and procurement to date; and the anticipated timeline for commencement of construction. [80263/26]

Comment on this

This question is to ask for an update on the delivery of DART+ South West, the progress made on funding and procurement to date and the anticipated timeline for the commencement of construction. As I have discussed with the Minister on many occasions, the area served by the Dublin-Kildare line, and what will be served by DART+ South West, has seen substantial residential development over the past few years. Congestion is an ever-present fact of life for many of my constituents. There is a real demand for increased public transport services. One of the pillars of this is DART+ South West. I would welcome the Minister's engagement on this project.

Comment on this

I thank Deputy Moynihan, who rightly says he has been advocating for this. It is a commitment we have made and we will deliver it. I want to put some context on it. If we look at budget 2027, there is agreement to invest another €6 billion in the delivery of MetroLink to 2030. The total public transport investment in the period is €18 billion. The progression of the DART+ programme, including DART+ South West, is a key part of this investment programme. I want to be really clear because I know there are some on the ground who are trying to stir up issues regarding DART+ South West. We are committed to it and we are going to do it.

DART+ South West will connect a number of major housing developments, including Clonburris and Adamstown, to a more frequent, higher-capacity public transport service, supporting decarbonisation and housing goals. National development plan funding has seen compulsory purchase orders proceed and commence along the DART+ South West and DART+ West corridors in February and September respectively this year. DART+ West will be the first major infrastructure element of the programme to enter heavy construction. As the Deputy knows, we started the enabling works last weekend and this is great to see.

What I expect on both projects, and it is really important that people understand this so I will say it on the floor of the House, is that they will go to the TII board. I expect the TII board to approve both projects together. They will then come to me. I expect to bring a memorandum to the Government in the coming weeks on DART+ South West and DART+ West. This will very clearly set out that we will be able to tender these projects together. One matter relates to the depot, which we know about, and the heavy civil works will all be tendered together. DART+ West and DART+ South West interlink so there are elements of staging and phasing. Anyone who thinks we are not committed to this project is incorrect. We are committed to it. I have met residents and constituents with Deputy Moynihan and I know the importance of the project. The Government is committed to both projects. Both will come to Cabinet in the coming weeks for formal approval and we can then move on to procurement.

Comment on this

I thank the Minister for the very encouraging update. As he knows, colleagues and I have been pushing consistently to see delivery of this programme. While we are waiting for the national development plan review we should not lose any time on procurement and moving forward to tendering. I welcome the Minister's announcement that all the packages for DART+ South West will go to tender at the same time as DART+ West. This means that as soon as funding is made available we will not lose any time.

Irish Rail appeared before the transport committee two weeks ago and I raised the same matter with it. It indicated to me that on this timetable it could see a contract possibly signed before the end of 2028, with services then in operation by 2034. This cannot come soon enough, and I have bent the Minister's ear about it enough over the past few months. For my constituents who rely on this, it is crucial. I welcome the announcement, which is a big step forward. I look forward to a further update from the Minister and I will come back to other things we can do in the short term in my next supplementary question.

Comment on this

I thank Deputy Moynihan. For the avoidance of any doubt on this, the contract frameworks for electrification, signalling and civil engineering works will be common across the programme. As Deputy Moynihan rightly said, this will help expedite the delivery of DART+ South West. This is exactly what we are going to do. There is phasing in the physical works and we have already started the DART+ West enabling works. It is a really exciting time for the delivery of major transport infrastructure projects throughout the country. These communities have fine homes, which we as a Government were involved in delivering, and it is now about providing additionality. In the coming weeks a memorandum to Government will clearly set out the contract frameworks I have outlined, including the civil engineering works, and these areas of work will be brought forward together.

Comment on this

I look forward to getting an update on the memorandum to the Government. I look forward to continued progress on this and I and others will continue to engage with the Minister on advancing the project. In the interim there are significant pressures on commuters who use Clondalkin-Fonthill, Adamstown, Kishoge and Hazelhatch stations. I noted the Minister's earlier comments about the prioritisation of additional carriages for the Dublin-Kildare line. I ask for his support in getting as many of these as possible onto the line because of the substantial residential development we are seeing, particularly in my constituency.

After a lot of campaigning, I am pleased the NTA has made progress on designing new bus routes for Adamstown and Clonburris to help take some of the short-term pressure off. We had the consultation earlier this year. This is something I have been advocating since being elected. I hope to get the Minister's support for funding to get these routes up and running as soon as possible. We want to make public transport the go-to habit of choice and we have to put these services in place to respond to it. I acknowledge the huge investment the Government has made in public transport and I want to see us go further. I ask for the Minister's support for additional carriages on the Dublin-Kildare line and funding for the Adamstown-Clonburris routes designed by the NTA.

Comment on this

On the DART+ fleet and the new carriages we are getting, which will assist right across the country, we have placed an order for 285 electric battery-charged carriages. The first order of 95 is now in testing. We have lodged the application with the European rail safety agency on the basis of the testing to approve these trains for the tracks. They will run first on the northern Belfast-Dublin line, serving Donabate, Malahide and Portmarnock into the city and then further north to Drogheda. This will enable us to redeploy good carriages and good rolling stock to other areas. Heavy usage areas will be a priority. Earlier I mentioned Cork, the greater Dublin area, Kildare and Dublin. This is just the first 95 carriages and we have 285 in total. On the NTA service plan for the provision of additional bus services, the Ministers of State, Deputies Buttimer and Canney, and I will be going through that in detail.

I met with the NTA directly last Friday. That relates to the new services that will be rolled out. I expect that to be published in December. It takes on board the feedback Deputy Moynihan and other Deputies have given us.

Comment on this