Written answer
Public Transport
120. Deputy Sean Fleming asked the Minister for Transport for a report on the projects and programmes that have been designated as critical infrastructure. [75690/26]
Comment on this
Designation under the Critical Infrastructure Act 2026 requires all public bodies to do everything within their power to accelerate any decision-making processes associated with the Programme.
Three major Transport projects were designated in the first round by my colleague the Minister for Department of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation.
• MetroLink
• Cork Commuter Rail
• The Galway City Ring Road
An update on each programme as of November 2026 is provided below:
MetroLink
On 16th September 2026, the Government consented to Approval Gate 2 for MetroLink. This enables MetroLink to proceed to the main procurement phase, with the main tender packs expected to proceed to market in the first half of 2027. Heavy construction under the main procurement contracts is expected to start in 2028.
In Budget 2027, the Government announced an additional €6 billion for MetroLink for the period from 2027 to 2030, to finance the project for construction.
A number of tenders to deliver advance and enabling works such as site clearance, utility diversions and archaeological services are issuing to the market. Initial enabling works, including utility diversions, will start on site in Dublin from early next year.
In addition to Approval Gate 2 consent from Government as referred to above, substantial progress has been made on MetroLink this year, including:
• In January, the Government approved the MetroLink Design and Tender Fee Scheme, which is designed to facilitate a competitive public procurement process and put downward pressure on the total project costs.
• Also in January, a potential legal challenge to the MetroLink Railway Order (granted in October 2025) was resolved, making the Railway Order enforceable and enabling MetroLink to progress towards procurement.
• Advertising procurement to shortlist tenders for the two civil works contracts, M401 and M402, commenced on 3 February 2026, with the publication of the PQQ. TII has since concluded the shortlisting of qualified tenders for the M401 and M402 contract packages. The Department understands there are four suitable bidders short-listed.
• In May, TII launched the M120 contract framework, which will include the construction of the Dublin Airport station box.
• Also in May, the Pre-Qualification Questionnaire (PQQ) for the M500 contract package was published, which marks the commencement of short-listing of qualified bidders for this contract, ahead of more detailed procurement.
• In June, the Government agreed to establish a dedicated Agency which will oversee the delivery of MetroLink, taking over from Transport Infrastructure Ireland. This will ensure a singular organisational focus on delivering the project to the approved scope, budget and cost. The necessary legislation to establish the new Agency is now being progressed. The Department is liaising closely with the Office of Parliamentary Counsel to the Government, who have assigned two drafters to the Bill, demonstrating its importance. It is hoped this Bill will be drafted by the year end and enacted in the first half of the year.
• TII has acquired a critical swathe of land spanning some 200 metres of continuous frontage along O’Connell Street in Dublin’s North Inner City, to facilitate the development of MetroLink. This commercial deal brings this site into state ownership, securing the regeneration of Dublin’s North Inner City and its flagship boulevard, O’Connell Street.
• On 10th September, Jacobs and Aecom were announced as the Project Delivery Partner for MetroLink. They will have a key role in overseeing the management of MetroLink though the construction stage. The contract is worth up to €550 million over 12 years.
Cork Area Commuter Rail Programme
The Cork Area Commuter Rail Programme is a key project in the Cork Metropolitan Area Transport Strategy 2040.
Phase 1 of the Programme consists of a signalling upgrade, construction of a through-platform at Kent Station, and double-tracking from Glounthaune to Midleton. This phase received EU funding of €164m through the Recovery and Resilience Facility and is expected to be substantially complete this year ahead of full commissioning in late 2027 or early 2028. The through-platform at Kent Station is already operational, opening in April 2025.
NDP funding will support the progression and delivery of Phase 2 of the Programme, which will build on the foundational investments made in Phase 1 to deliver a new depot to support an electrified, a new depot, electrification works, and up to eight new stations. Subject to relevant approvals, a Railway Order planning application for the programme is expected to be submitted to An Coimisiún Pleanála in early 2027.
In advance of submitting this Railway Order, a planning application for Dunkettle station has been submitted to Cork City Council and local planning permission was granted by Cork City Council for a new station at Blackpool in September.
Funding announced under the Housing Infrastructure Investment Fund (HIIF) in November will support the accelerated delivery of two more stations at Blarney and Water-Rock, subject to planning permission. These stations will support residential development at both locations and complement the separate HIIF funded project in Water Rock designed to unlock lands for over 3,800 new homes, with the potential for a further 1,600 new homes.
In total, it is anticipated that four new stations, Blackpool, Dunkettle, Blarney and Water-Rock, will be operational on the network by the end of 2029.
Galway City Ring Road
The proposed Galway City Ring Road project comprises 12.5km of motorway between the existing N6 at Coolagh (north east of the city) to the existing Ballymoneen Road (northwest of the city) and continues as a single carriageway road for a further 5km of protected road, west of Bearna. The new orbital route travels around the city and will include a new bridge crossing of the River Corrib. This project will divert traffic away from Galway city.
An Coimisiún Pleanála (ACP) approved the scheme on 09 April 2026. The final High Court judicial review and legal challenges against the project were officially withdrawn in November 2026.
A procurement strategy is under preparation. This project has been allocated €4.45 million for 2026.
This is the first road project to have received designation as critical infrastructure. This will mean that the project will be supported by closer inter-departmental and inter-agency cooperation and allow for avoidable delays to be reduced while retaining all legal, planning and environmental requirements.