Flood Risk Management

223. Deputy Cathal Crowe asked the Minister for Transport the status of the 2020 design study to address recurring flooding on the Limerick-to-Ennis railway line at Ballycar, County Clare; if his Department will engage with Clare County Council and the Office of Public Works to formally designate a lead agency to progress these works; and the funding streams available to implement the flood mitigation design. [80337/26]

Comment on this
Darragh O'Brien Minister for Transport Fianna Fáil

As Minister of Transport, I have responsibility for policy and overall funding of public transport. The operation, maintenance and renewal of the rail network and stations on the network, is a matter for Iarnród Éireann in the first instance.

Given Iarnród Éireann's responsibility in this matter, I have referred the Deputy's question to the company for direct, detailed reply. Please contact my private office if you do not receive a reply within 10 working days.

In relation to flood alleviation at Ballycar, officials from my Department are engaging with all relevant stakeholders including Iarnród Éireann and the National Transport Authority on how best to address the long-term issue of flooding on the railway line, which is likely to require significant engineering works.

In identifying the preferred solution, my Department together with Iarnród Éireann may also seek to engage with the Office of Public Works to seek their advice and engineering expertise on potential solutions.