Schools Building Projects

261. Deputy Louis O'Hara asked the Minister for Education and Youth if an application under the climate action summer works scheme has been received from a school (details supplied); if that application has been assessed; if not, the reason the application was not assessed prior to the announcement of successful schools under the scheme; whether there is any mechanism through which the board of management could seek reimbursement of the costs incurred in preparing their application (€2000 for professional engineer services); and if their application can be granted approval in light of the circumstances. [80423/26]

Comment on this
Hildegarde Naughton Minister for Education and Youth Fine Gael

The purpose of the Climate Action Summer Works Scheme (CASWS) is to enable individual school authorities to undertake small-scale building works on a devolved basis that, ideally, can be carried out during the summer months or at other times that avoid disrupting the operation of the school. The CASWS operates on a multi-annual basis across a number of categories of works.

It is envisaged that approvals in any given year will involve a spread of categories rather than the traditional single category at a time. This is aimed at managing market capacity and maximising value for money opportunities for school authorities.

In November 2026, my department announced the second tranche of approvals under the Climate Action Summer Works Scheme. 229 projects were approved to proceed and involve primary, post primary and special schools, along with projects in all counties and across all categories of works. This constitutes an investment of €80m across the school network for 2027 under the scheme.

My department can confirm an application was received from the school in question however the school was not on the list of approvals in the second tranche. Given that funding is limited in any particular year it is necessary to prioritise applications. Under the climate action summer works scheme which operates on a multi annual basis, like previous summer works schemes, applications from schools that are not reached for funding or market prioritisation reasons in 2027 will qualify to be assessed for purposes of the funding available for climate action summer works in subsequent years.

A Consultant’s technical report must accompany all applications, the report is necessary in order to:

• provide a professional diagnosis of the full nature and extent of the proposed project.

• verify the absolute necessity for the project relative to the impact of not doing it.

• provide a detailed breakdown of the cost. A breakdown of costs must be provided, including costs per m² of building area affected by the proposed works.

• inform the prioritisation of projects on the basis of professional objective information.

As per the circular governing the scheme the appointment of a consultant is a matter for the school authority and any fees arising must be borne by the school.

It is anticipated that the next tranche of approvals will be announced in the latter part of 2027.

Full details of the announcement, the list of schools approved in the first and second tranche, the Circular (0029/2025) for the scheme and guidance documents for schools can be found at the below link; www.gov.ie/en/department-of-education/services/summer-works-scheme/.[]