Nithe i dtosach suíonna - Commencement Matters ›
Road Network
Senator Mike Kennelly called for urgent repairs to the deteriorating N69, citing safety risks for motorists, pedestrians and cyclists. The Minister said TII’s 2027–29 pavement programme includes sections near Cahirdown and Kilflynn, and undertook to press for priority intervention with Kerry County Council, subject to funding.
I thank the Minister of State for coming to the Seanad this morning. Today, unfortunately, I again want to highlight an issue I have spoken about on a number of occasions since I became a Senator representing Kerry. It is the worsening condition of the N69 running into Kerry, which is one of the most important transport routes serving north Kerry and west Limerick. I have raised the condition of this road on a number of occasions and, unfortunately, the situation continues to deteriorate. Earlier this year, I raised the deplorable condition of the N69 from Bolton’s Cross to the Tim Kennelly roundabout in Listowel. At that time, I spoke about the seven years of delay, broken promises and frustration of local people, who simply want a safe and properly maintained national road. Unfortunately, since then the situation has not improved. In fact, it has deteriorated further.
What was once a problem associated with particular sections of the road is now becoming a much wider issue. Significant sections of the N69 between Tarbert, entering from west Limerick, and Listowel are showing serious signs of wear and deterioration, with potholes, uneven surfaces, rutting and other road defects. There are a lot of undulations on the N69. Sections of that N69 are not on the Golden Vale, as I always say. The dry summer we had caused a lot of undulations throughout our road network, but it is an especially big issue on the N69 sections I mentioned, which are very unsafe. There are also significant concerns about the conditions of the road farther along the route, including sections around the Kilflynn area and heading towards Pope's Cross in Tralee.
This raises a very simple question. Who is allowing the ball to be dropped here? Last year, Kerry County Council identified the N69 as the number three priority on its list for national roads investment, yet despite being identified locally as a priority, the road did not receive the funding required to address the deterioration. My question for the Minister of State, the Department of Transport and Transport Infrastructure Ireland, TII, is, where is the disconnect? If Kerry County Council is identifying the N69 as one of its top priorities but the necessary funding is not being secured at a national level, who is responsible for making sure this important national route gets the investment it requires?
The N69 is a national road. It is a major transport corridor connecting Tarbert, Listowel and Tralee and serving communities right across north Kerry and west Limerick. It carries workers travelling to their jobs, parents bringing children to school, farmers transporting livestock and produce, tourists travelling through the county and heavy goods vehicles supporting local businesses and industry. When a national road is allowed to deteriorate to this extent, it is not simply an inconvenience. It becomes a road safety issue. It places unnecessary costs on motorists through vehicle damage and creates a poor first impression of the region for visitors and tourists. I am particularly concerned about the section at Cahirdown in Listowel, which is among the worst affected areas. There are sections where footpaths are provided but there is inadequate lighting. People are walking and cycling alongside a road that is already in poor condition, creating an unacceptable combination of road safety concerns.
When funding is being assessed and allocated, we cannot simply look at the cost of resurfacing a road.
We also need to look at the full safety picture, including the condition of the road, pedestrian infrastructure, lighting, visibility and the interaction between vehicles and vulnerable road users. Safety must be central to the costing and prioritisation of these works. The people of north Kerry have shown a lot of patience in this regard. They have reported the problems, raised the concerns through their local representatives and waited year after year for action. They want funding secured and work delivered. I am, therefore, calling on the Minister of State, Deputy Canney, and TII to urgently review the N69 from Tarbet through Listowel and onwards to Tralee, identify the sections requiring immediate intervention and, most importantly, secure the necessary funding to carry out these works.
I raised this matter when I was a county councillor. I have been jumping up and down about it. We have been neglected and ignored. It has gone on far too long. Another year of the Listowel Races has come and gone with thousands of people from the west coming down the N69. It is not safe to face that road. It has deteriorated to an unbelievable standard. I am calling for urgent support for this road.
Comment on this
I thank the Senator for his Commencement matter. The matter of infrastructure investment to support road safety, as well as the quality of life for people who rely on the N69, is important for both me and the Department. The Minister for Transport has responsibility for overall policy and Exchequer funding on the national roads programme. Once funding arrangements have been put in place with TII under the Roads Acts, and in line with the national development plan, NDP, the planning, design, improvement and upgrading of individual national roads is a matter for TII in conjunction with the local authorities concerned. TII ultimately delivers the national roads programme in line with Project Ireland 2040, the national planning framework and the NDP.
It is important to point out that a number of major projects have been delivered under the current NDP, including the Listowel bypass and the Baile Bhuirne to Macroom project. These projects have resulted in improved connectivity for Kerry and the wider region. Approximately €659 million of Exchequer capital funds were provided for national roads through TII to local authorities in 2026. This is used for the construction of major new roads projects as well as the protection and renewal of the existing network. Of this funding, over €33 million was allocated to Kerry County Council. A major priority in the NDP, in line with the Department’s investment hierarchy, is to maintain the quality and safety of the existing national road network. This includes funding for minor improvement projects, safety schemes, such as junction upgrades and road realignment, and pavement renewal.
Regarding the N69, TII has prepared a new three-year investment programme for the period from 2027 to 2029, identifying the locations and interventions required to address the network’s priority pavement renewal and maintenance needs. As part of this asset renewal programme, there are a number of schemes identified on the N69 at Skehanierin - I might not be pronouncing that correctly – to Cahirdown and around Kilflyn over the three-year period.
In respect of programming, TII works with local authorities in prioritising individual sections for renewal. However, as always, the programme and associated improvements in network condition will be contingent on the provision of sufficient and sustained funding on a year-on-year basis over the period, with funding levels determining the extent to which the identified requirements can be progressed. TII will work closely with Kerry County Council to identify critical areas for intervention both on this road and other national routes in Kerry, subject to available funding.
I hope this information is of assistance to the Senator. I feel the passion in his ask. As he said, this is not the first time he has raised this matter. I will take it up with TII to determine where this project is at. I am responsible for road safety and I wish to ensure that safety for roads is maintained to the highest level possible. We have a role to play in determining that. I will come back to the Senator in that regard.
Comment on this
I thank the Minister of State for his response. I am delighted to hear the new three-year pavement programme for the period from 2027 to 2029 includes the section of road between Skehanierin and Cahirdown. The area around Bolton’s Cross, to the Tim Kennelly roundabout and on to Kilflyn, is where the real dangers lie. This is wonderful news, but I ask that we prioritise and double down on this so that works will commence in early 2027 on that location from Bolton’s Cross onwards, which is the most dangerous part, especially for pedestrians and road users. It is wonderful news. I sincerely thank the Minister of State and I hope all conditions on that road will be safe to travel on by 2029.
Comment on this
I thank the Senator for the correct pronunciation of that placename. When I get down there to have a look at the road, I will have the correct pronunciation.
Comment on this
The Minister of State will be welcome.
Comment on this
We will continue to work with TII. As I said, a three-year programme is in place. Sections have been identified in conjunction with the county council and will be prioritised next year. I hope that will happen. I will contact TII through my officials to ensure that this is prioritised because from the description the Senator provided, this is not only about having a safe road but also ensuring pedestrians and cyclists are safe. We will continue to work on that.
It is important to mention that other major projects in Kerry are being planned. The protection and renewal of the existing road network is important to us, as is progressing major projects. A total of €32 million in capital Exchequer funding was allocated for the national road network in County Kerry. This funds the protection and renewal of existing roads as well as the development of new roads, including the N22 Killarney to Farranfore project that is on the cards. This is in keeping with the programme for Government initiatives and our determination to deliver rather than merely talk about delivering. What the Senator is talking about is delivery for the sections in question. I look forward to engaging with the Senator again in this regard.